1. OFFICE MEMORANDUM
2. NATIONAL RIVER CONSERVATION PLAN (NRCP)
SCHEME
3. OFFICE MEMORANDUM(NLCP)
4. NATIONAL LAKE CONSERVATION PLAN (NLCP)
SCHEME
5.
REVISED GUIDE LINES FOR
PREPARATION OF DPRs FORCONSERVATION OF RIVERS & LAKES
8.
CHAPTER III ; INVESTIGATIONS FOR DPR PREPRARATION
9.
CHAPTER IV: DESIGN OF SYSTEM AND COMPONENTS
10. CHAPTER V : OPERATION & MAINTENANCE
11. CHAPTER VI
: PUBLIC AWARENESS. & PUBLIC PARTICIPATION:
12. CHAPTER VII
: HRD AND CAPACITY BUILDING
13. CHAPTER
VIII : PROJECT MANAGEMENT & INSTITUTIONAL ISSUES
15. CHAPTER X :
MONITORING & EVALUATION
16. CHAPTER XI
: COST ESTIMATES AND GENERAL REQUIREMENTS OF DPRS
17. ANNEXURE I : RESOLUTIONS ADOPTED AT THE XTH MEETING OF THE
NRCA – MARCH’2001 – PM IN CHAIR.
18.
ANNEXURE II : GUIDELINES
FOR PREPARATION OF SCHEMES OF LOW
19.
COST SANITATION (LCS)
20. ANNEXURE III :GUIDELINES FOR PREPARATION OF SCHEMES OF SOLID WASTE MANAGEMENT
UNDER RIVER PLAN
22. ANNEXURE V Norms for Staff & Staff
Quarters Required on Sewage Pumping Stations & STPs
23.
ANNEXURE VI GUIDELINES FOR PUBLIC AWARENESS AND PUBLIC
PARTICIPATION IN NATIONAL RIVER ACTION PLAN SCHEMES OF THE MINISTRY OF ENVIRONMENT
AND FORESTS
24. ANNEXURE
VIII-A :COMPLETION REPORT (General Abstract of Cost)
26. Ministry of Environment & Forests
UTILISATION CERTIFICATE
G.11011/2/2001-NRCD.I
Ministry of Environment & Forests
National River Conservation Directorate (NRCD)
Dated 13th August 2002
OFFICE
MEMORANDUM
SUBJECT: NATIONAL RIVER
CONSERVATION PLAN (NRCP) SCHEME – CONTINUATION
IN TENTH
PLAN
As required by Department of Expenditure OMs no. 1(3)/PF. II/2001 dated 10th May 2002 and 10th July 2002, the matter of continuation of National River Conservation Plan (NRCP) Scheme in 10th Plan has been examined in consultation with JS&FA, and it has been decided to continue the NRCP scheme during 10th Plan.
A copy of the NRCP Scheme and its guidelines is enclosed.
This issues with JS&FA’s concurrence vide his diary no. 1033/JS&FA/F 102 dated 12-08-02
Sd/-
(Dr. Ms. Manju Raina)
Joint Director
G.11011/2/2001 – NRCD. I
Ministry of Environment & Forests
National River Conservation Directorate (NRCD)
NATIONAL RIVER CONSERVATION PLAN (NRCP) SCHEME
1.0
Objective
To improve the water quality of major rivers, which are the major fresh water source in the country, through the implementation of pollution abatement schemes.
2.0
Brief History
The river-cleaning programme of the Ministry of Environment and Forests was started with the launching of the Ganga Action Plan GAP) in 1985. A Central Ganga Authority under the Prime Minister was constituted to finalize the policy framework and to oversee the implementation of the Action Plan. Chief Ministries of concerned States, Union Ministers and Secretaries of the concerned Central Ministries and experts were its members. GAP was later extended to GAP Phase-II in 1993 and then to NRCP in 1995. GAP Phase-II was merged into NRCP in December 1996. Since then a single scheme of NRCP is under implementation as a Centrally Sponsored Scheme. The CGA was re-named as National River Conservation Authority (NRCA) with a larger mandate to cover all the programmes supported by the National River Conservation Directorate.
The functions of the NRCA are as follows:
i) To lay down, promote and approve appropriate policies and programmes (long and short-term) to achieve the objectives.
ii) To examine and approve the priorities of the National River Conservation Plan.
iii) To mobilize necessary financial resources.
iv) To review the progress of implementation of approved programmes and give necessary directions to the Steering Committee, and
v) To take all such measures as may be necessary to achieve the objectives.
Ganga Action Plan (GAP) Phase-I was started in 1985 as a 100% centrally funded scheme. The main objective of GAP was to improve the water quality of Ganga to acceptable standards by preventing the pollution load reaching the river. Under GAP Phase-I pollution abatement works were taken up in 21 class-I towns in UP, Bihar and West Bengal. This Phase has been declared complete on 31st March 2000 at a cost of Rs. 451.70 crore.
GAP Phase-I was extended to GAP Phase-II approved in stages between 1993 to 1996, which covered the river Ganga and its major tributaries viz., Yamuna, Gomati and Damodar. This action plan covers pollution abatement works in 95 towns along the polluted stretches of four rivers spread over seven States. The total approved cost of this action plan is Rs. 1498.86 crore which was approved on 50:50 cost sharing basis between the Centre and the State Governments.
Later, however, it was felt that the river conservation activity needed to be extended to other rivers of the country also. Accordingly, the existing scheme was merged into a National River
Conservation Plan. National River Conservation Plan (NRCP) was approved for Rs. 772.08 crore in 1995 on 50:50 cost sharing basis between the Centre and the State Government. The then Ganga Project Directorate was converted into National River Conservation Directorate for servicing the National River Conservation Authority and the Steering Committee. The objective of National River Conservation Plan being to improve the water quality of the major rivers which are the major fresh water source in the country through the implementation of pollution abatement schemes. It covered pollution abatement works in 46 towns along the polluted stretches of 18 rivers spread over 10 States. The Ganga Action Plan Phase-II was merged with NRCP in December 1996. Seven additional towns of Tamil Nadu were approved in January 2001 at a cost of Rs. 575.30 crore on this funding pattern.
NRCP was converted into a 100% centrally funded scheme on the lines of GAP Phase –I in November 1998. The land cost was however, to be borne by the States. Chennai Waterways in Tamil Nadu were approved in September 2000 at a cost of Rs. 491.52 crore and Yamuna Action Plan (extended phase) was approved in May, 2001 at a cost of Rs. 222.60 crore based on this funding pattern.
In a meeting of the National River Conservation Authority held in March, 2001 under the Chairmanship of Prime Minister of India., it was decided to adopt an integrated approach for the river cleaning programmes; and that all future works would be shared on a 70:30 basis between the Centre and the State Governments. Of the State share, the share of public shall be minimum of 10% of the total costs..
The chronology of approval and cost of various components of NRCP is given below:
|
S. No. |
Component |
Approved cost with 50:50 funding/ date of approval |
Present approved cost on 100% funding, Cost sharing / date of approval by CCEA |
|
1. |
Yamuna Action Plan |
357.00/April 93 |
- |
|
2. |
Gomati Action Plan |
64.00/April 93 |
61.11/Nov 98 |
|
3. |
CETP, Calcutta |
65.00/Aug 95 |
65.00/Nov 98 |
|
4. |
National River Conservation Plan |
772.09/July 95 |
737.14/Nov 98 |
|
5. |
GAP-II(Main Stem including West Bengal) |
416.36/ Oct 96 |
396.16/Nov 98 |
|
6. |
Yamuna Action Plan (first revision) |
479.56/April 96 |
- |
|
7. |
Damodar Action Plan |
24.54/Oct 96 |
23.58/ Nov 98 |
|
8. |
GAP-II (SC towns) |
231.70/Oct 96 |
220.96/ Nov 98 |
|
9. |
Yamuna Action Plan(2nd revision) |
526.71/Sept 98 |
509.45/Nov 98 |
|
10. |
Chennai Waterways |
|
491.52/Sept 2000 |
|
11. |
7 additional towns of Tamil Nadu |
|
575.30(cost sharing) / January 2001 |
|
12. |
Yamuna Action Plan (Extended Phase) |
|
222.60 / May 2001 |
|
13. |
2 additional towns of Punjab |
|
14.97 (70:30) / July 2001 |
|
14. |
1 additional town of Maharashtra |
|
11.64(70:30)/08.01.02 |
|
15. |
1 Additional town of Goa |
|
14.09(70:30)/27.05.02 |
|
|
|
Total |
3343.52 |
3.0
Activities covered
The activities under NRCP include the following: -
· Interception and Diversion works to capture the raw sewage flowing into the river through open drains and divert them for treatment.
· Sewage Treatment Plants for treating the diverted sewage.
· Low Cost Sanitation works to prevent open defecation on riverbanks.
· Electric Crematoria and Improved Wood Crematoria to conserve the use of wood and help in ensuring proper cremation of bodies brought to the burning ghats.
· River Front Development works such as improvement of bathing ghats.
· Public awareness and public participation.
· HRD, capacity building, training and research in the area of River Conservation.
· Other miscellaneous works depend upon location specific conditions including the interface with human population.
4.0
Funding Pattern
· NRCD/Government of India shall bear upto 70% of the Project cost.
· States and Local Bodies shall bear 30% of the Project cost of which the share of public would be a minimum of 10% to ensure public participation in the project.
· The O&M shall be a part of the project and the costs thereon shall be borne entirely by the State and local bodies for which additional resources have to be demonstrably raised and committed to O&M.
· The Local Bodies may raise loans from financial institutions such as HUDCO to contribute their share.
· If there is a cost overrun in a project because of delay, inflation or any other reason, the contribution of NRCD/Government shall be limited to its contribution amount initially agreed. Any additional expense on account of any increase in cost shall be borne by the concerned State Government.
· In addition NRCD/Government of India may undertake itself or commission projects to other institutions, voluntary agencies etc. also.
5.0
Mechanism of
implementation and monitoring
Projects or River Action Plans are considered by the Govt. on the basis of pre-feasibility report estimates prepared by the State Govts. After the project is approved in principle, detailed project reports (DPR) with firmed up cost estimates for various sub-components are prepared by the State Govts./Project proponents. These DPRs are appraised and approved by the Ministry following which Administrative Approval and Expenditure Sanctions are issued. On the basis of these sanctions, the State Governments / implementing agencies award contracts according to their own policy and rules.
Progress of implementation is monitored by both the State Implementing Agencies and the Ministry through a multi-tier monitoring mechanism. This includes :
State Level
i) The progress monitoring by a team of field engineers on a day to day basis.
ii) Monthly review of progress at the Chief Executive level of the nodal implementing agency.
iii) Citizen’s Monitoring Committee in each town to review the progress and provide inputs for public participation and involvement.
iv) Periodical review by the Divisional Project Monitoring Cells.
v) Periodical review of progress by a State Steering Committee chaired by the concerned Chief Secretaries.
vi) Periodical review by a High Powered Committee under the Chairmanship of Chief Minister.
Central Level
i) Regular review by NRCD officials including frequent site visits.
ii) Regular review by NRCD Project Director.
iii) Quarterly review of progress by a Steering Committee headed by Secretary of the Ministry. Chief Secretaries of the concerned States and experts in the Public Health Engineering and other related areas are the members of this Committee.
iv) Quarterly review of progress of scientific and technical aspects of the programme as well as the impact of works on the river water quality by a Monitoring Committee headed by Members Environment, Planning Commission.
v) Periodical review by a Standing Committee of NRCA headed by the Union Minister of Environment & Forests.
vi) Periodical review of progress by the National River Conservation Authority headed by Prime Minister. The concerned Chief Ministers, among others, are the members of this Committee.
6.0 Further details of activities, funding pattern, mechanism of implementation and monitoring Project Preparation Guidelines etc. are given in the enclosed Guidelines
(Appendix B)
7.0
Year wise-Plan
Outlay and phasing of expenditure in the X Plan
Year Outlay (Rs. In crore)
2002-03 290.00
2003-04 290.00
2004-05 290.00
2005-06 290.00
2006-07 290.00
J.16011/8/2002-NRCD
Ministry of Environment & Forests
National River Conservation Directorate (NRCD)
Dated 13th August 2002
OFFICE
MEMORANDUM
SUBJECT: NATIONAL RIVER CONSERVATION
PLAN (NLCP)
SCHEME – CONTINUATION
IN TENTH
PLAN
As required by Department of Expenditure OMs no. 1(3)/PF. II/2001 dated 10th May 2002 and 10th July 2002, the matter of continuation of National Lake Conservation Plan (NLCP) Scheme in 10th Plan has been examined in consultation with JS&FA, and it has been decided to continue the NLCP scheme during 10th Plan.
A copy of the NLCP Scheme and its guidelines is enclosed.
This issues with JS&FA’s concurrence vide his diary no. 1032/JS&FA/F/2 dated 12-08-02
Sd/-
(Dr. (Mrs.) R Dalwani)
Additional Director
J.16011/8/2002 –
NRCD
Ministry of Environment & Forests
National River Conservation Directorate (NRCD)
NATIONAL LAKE CONSERVATION PLAN
(NLCP) SCHEME
1.0
Objective
The objective of the scheme is to restore and conserve the polluted and degraded urban lakes of the country. To begin with, NLCP proposes to cover urban lakes, especially those not covered under the Wetlands programme of the Ministry, with the scope of activities to be expanded to include the rural water bodies.
2.0
Brief History
2.1 The Ministry of Environment & Forests had identified 10 polluted urban lakes for conservation and management in 1994. The details of these lakes are given below:
|
SI |
Lake |
State |
Cost (Rs. In Crores) |
|
1 |
Dal |
J&K |
297.70 |
|
2 |
Sukhna |
Chandigarh |
44.36 |
|
3 |
Sagar |
MP |
4.41 |
|
4 |
Nainital |
UP(Uttaranchal) |
46.35 |
|
5 |
Kodai Kanal |
Tamilnadu |
19.28 |
|
6 |
Ooty |
Tamilnadu |
26.63 |
|
7 |
Udaipur |
Rajasthan |
148.95 |
|
8 |
Rabindra Sarovar |
West Bengal |
2.13 |
|
9 |
Powai |
Maharashtra |
31.01 |
|
10 |
Hussain Sagar |
Andhra Pradesh |
15.34 |
|
|
|
TOTAL |
636.16 |
Vide Deputy Chairman’s DO no. 15050/6/93E&F/DCH/13/6369 dated 29th July 1997, the Planning Commission conveyed the approval of NLCP as a 100% Centrally Sponsored Scheme. Accordingly, a note covering the aforesaid 10 polluted urban lakes at an estimated cost of Rs. 637 crore was put up for approval of CCEA at its meeting held on 29.12.1997. CCEA considered the note and directed the Ministry of Environment & Forests to bring up the matter for consideration after a fresh appraisal of the scheme in the light of a firm tie up of external financial assistance for financing NLCP. The Committee, however, approved, in principle, the proposal to take up the scheme for conservation of the Dal Lake and decided that an amount upto Rs. 20 crore may be spent on land acquisition which are considered absolutely necessary by way of advance action for speedy implementation of the scheme in so far as it relates to the Dal Lake.
2.2 The Ministry posed NLCP for financial assistance to some of the bilateral multi-lateral funding agencies viz; the World Bank, the Japan Bank for International Cooperation, the Government of Netherlands, the Government of Austria and European Commission, However, none of these agencies evinced interest in the proposal.
2.3 Meanwhile, a High Power Committee under the Chairmanship of Union Home Minister at its meeting held at Srinagar on 24.6.1998, decided that in the background of the Cabinet decision on NLCP, the Planning Commission should look into it for purposes of financing the Dal Lake Conservation Plan (DLCP) through internal resources. As suggested by the Planning Commission, a detailed project report (DPR) on DLCP has been prepared at an estimated cost of Rs. 162.87 crore. The cost of the DLCP, after adding land cost of Rs. 87.10 crore for structures within and outside the lake body, shall be Rs. 249.97 crore. The DPR was sent to the State Government in November 2000. The response of the State Government on the DPR is awaited. On receipt of the comments from the State Government, the proposal will be put up to the EFC and then to CCEA for consideration and approval.
2.4 So far as the status of other identified lakes of NLCP is concerned, conservation and managements plans of 3 lakes namely, Powai, Ooty and Kodaikanal were approved under NLCP by CCEA in June 2001 at a cost of Rs. 14.90 crore, and the condition of external assistance for NCLP was waived. These projects are under implementation. A conservation and management plan for the Rabindra Sarovar lake at Calcutta has been received and is under consideration in the Ministry. The Government of Uttaranchal has appointed consultants for preparation of a DPR for the conservation and management plan of Nainital Lake. As far the Hussain Sagar lake in Hyderabad, most of the works have already been taken up by the State government under a separate scheme funded by the World Bank. The Detailed Project Report for the remaining 3 lakes namely, Sagar, Udaipur and Sukhna are yet to be received.
2.5 Meanwhile, in view of the several proposals received from State Governments for other lakes and availability of funds under NLCP, it has been decided to take up such lakes depending on the pollution status as well as availability of funds. Proposals for 4 lakes in Bangalore city namely, Jaraganahalli, Kamakshipalya, Nagavara and Vengainahakere have been approved at a total cost of Rs. 12.32 crore. A proposal for Man Sagar lake in Jaipur is also under consideration. Similar proposals for other lakes would be taken up subject to availability of funds.
3.0
Activities covered
The activities under NLCP include the following: -
(i) Prevention of pollution from point sources by intercepting, diverting and treating the pollution loads entering the lake.
(ii) In situ measures of lake cleaning such as Desilting, Deweeding, Bioremediation, constructed wetland approach etc. depending upon the site conditions.
(iii) Catchment area treatment and lake beautification which may include bunding, fencing creation of facilities for public recreation and entertainment (children park, boating etc.) and public area.
(iv) Public awareness and public participation.
(v) HRD, capacity building, training and research in the area of Lake Conservation.
(vi) Other activities depend upon location specific conditions including the interface with human population.
State Governments or other Project Proponents would get perspective plans and detailed Project Reports (DPRs) prepared through consultant or otherwise, for the above and for conservation based on surveys including water quality and biodiversity data.
4.0
Funding Pattern
a. NRCD/Government of India shall bear upto 70% of the Project cost.
b. States and Local Bodies shall bear 30% of the Project cost of which the share of public would be a minimum of 10% to ensure public participation in the project.
c. The O&M shall be a part of the project and the costs thereon shall be borne entirely by the State and local bodies for which additional resources have to be demonstrably raised and committed to O&M.
d. The Local Bodies may raise loans from financial institutions such as HUDCO to contribute their share.
e. If there is a cost overrun in a project because of delay, inflation or any other reason, the contribution of NRCD/Government shall be limited to its contribution amount initially agreed. Any additional expenses on account of any increase in cost shall be borne by the concerned State Government.
f. NRCD/Government of India may also undertake itself or commission projects to other institutions, voluntary agencies etc.
5.0 Further details of activities, funding
pattern, mechanism of implementation and monitoring Project Preparation
Guidelines etc. are given in the enclosed Guidelines (Appendix)
6.0 Yearwise-Plan Outlay and
phasing of expenditure in the X Plan
A total outlay of Rs. 150 crore has been approved for NLCP during the X Plan with an annual outlay of Rs. 30 crore for the current financial year (2002-03). Rs. 30 crore per year is envisaged to be the plan outlay for each of the other years of the plan.
REVISED GUIDE LINES FOR PREPARATION OF DPRs
FOR
CONSERVATION OF RIVERS &
LAKES
1.1 The National River Conservation Directorate in the Ministry of Environment & Forests had prescribed guidelines for the preparation of the Project Feasibility and the Detailed Project Reports under the National River Conservation Plan. Since then a number of developments have taken place including the resolutions passed by the National River Conservation Authority (NRCA) in its meeting held in March 2001 (Annexure I). It has therefore, been decided to issue new guidelines for the preparation of Detailed Project Reports under the National River Conservation Plan and the National Lake Conservation Plan consolidating the decisions taken from time to time. Since the proposals in future will be considered on the basis of DPRs only, PFR are not to be submitted to the NRCD and so the guidelines for preparing the PFRs are not being issued. These guidelines supercede earlier guidelines and should be followed.
1.2 The DPR should consist of
1.2.1 A review of the status of the river/lake system
1.2.2 Identification of degraded stretches & towns responsible for it.
1.2.3 Selection of Towns in order of priority where conservation works should be taken up and the justification for their selection.
1.2.4 Collection of information about the river/lake and basin/ catchment useful for system and component design.
1.2.5 Investigation carried out for DPR Preparation
1.2.6 Design of System and components
1.2.7 Human, physical and financial resources required for Operation & Maintenance and the manner in which they will be ensured.
1.2.8 Plan for Public Awareness & Public participation:
1.2.9 Plan for HRD and Capacity Building
1.2.10 Plan for project management & dealing with institutional issues identified
1.2.11 Plan to finance the project
1.2.12 Monitoring & Evaluation plan
1.2.13 Cost Estimates of DPRs with drawings and specifications
1.2.14 Any other item considered relevant and useful.
2. Priority
lists of rivers/lakes and towns/cities
2.1 While the causes of degradation of rivers and lakes are many, the towns and cities on their banks with beaming population and industry are the most significant sources of degradation of rivers, lakes and seas. In view of the limited resources available, it is not possible to take up all degraded rivers and lakes for conservation together. It is, therefore, necessary to prepare lists indicating priority of river/lakes and also of the cities/towns where conservation programmes would be taken up in the X plan.
2.2 In order to select the river / lakes and cities / towns and arrange them in order of priority for this programme, studies are required to be made based on the relevant data / information. After the river / lake system has been studied and the major sources of degradation identified, the cities on the banks responsible for their severe degradation components need to be collected for preparing the DPR.
2.3
Collection of
data/information
The following information of river/lake and basin/catchment is useful:
2.3.1 Area of the basin / catchment of the river/lake.
2.3.2 Topography
2.3.3 Climate including rainfall,
2.3.4 Land Use
2.3.4.1 Agriculture,
2.3.4.2 Forests,
2.3.4.3 Mining
2.3.4.4 Residential, commercial and industrial
2.3.5 Status of Ground Water development and use
2.3.6 Dams and diversion works
2.3.7 Discharge figures if the water body is gauged
2.3.8 Abstraction of water
2.3.9 Morphology and hydrology of the water body
2.3.10 Water quality of the water body in its different reaches
2.3.11 Aquatic life present in the water body in different stretches of the water body
2.3.12 Traditional and current uses to which the water body is put in different reaches
2.3.13 Economic, culture and religious significance of the water body and the towns located on it.
2.3.14 Towns with population exceeding one hundred thousand located on the river. For each such town
2.3.14.1. Population in last census,
2.3.14.2. Status of water supply,
2.3.14.3. Sewerage,
2.3.14.4. Drainage,
2.3.14.5. Garbage and bio-medical waste and
2.3.14.6. Industrial effluent disposal.
2.4
Use of Available Sources
2.4.1 The above data may be collected from available sources and presented in figures, charts and maps along description in brief.
2.4.2 If some of the information is not available or not adequate, fresh studies should be undertaken only if it is felt that in the absence of the missing information, the work of selecting the river/lake and the cities cannot be done.
2.5
Use of modern tools GIS
2.5.1 If there are easily accessible facilities attempt should be made to use remote sensing and present the spatial information in Geographical Information System (GIS) format.
2.6 Criteria for Selecting a river/lake for
Conservation:
A lake/river may be selected for conservation under the NRCP/NLCP if
2.5.1 the water body-river, lake or the sea - - is so degraded that it cannot be put to its traditional and desired use
2.5.2 the people are strongly aware of the degradation
2.5.3 they highly value the restoration of the water body
2.7 Criteria for
selecting towns for taking up Conservation of rivers and lakes
Works may be proposed in a town if
2.7.1 The town is located on the bank of river or lake or is a coastal town.
2.7.2 The population of the town is at least one lakh.
2.7.3 The water body (river/lake) is highly degraded and cannot be put to its traditional/designated use because of
2.7.3.1 Discharge of domestic waste water/industrial waste
2.7.3.2 municipal solid waste
2.7.3.3 other non-point sources of pollution
2.7.4 The flood plain is heavily encroached
2.7.5 Wrong land use in violation of the Master Plan leading to heavy soil erosion and sediment transport to the water body.
2.7.6 There is high level of awareness about the city being the major cause of degradation of the water body leading to the demand from the residents of the town to take up conservation measures.
2.7.7 The citizens are willing to demonstrably raise additional resources and make financial contribution of a minimum of 10% of the project cost and to meet the recurring expenses of O& M and other heads.
2.7.8 The local body is willing to make its contribution and take responsibility for preparing and implementing the project and carrying out O&M at its own cost.
2.7.9 The residents of the town, the local body and the State Government together are willing to contribute a minimum of 30% of the project cost, out of which the citizens are willing to contribute a minimum of 10% of the project cost.
CHAPTER
III ; INVESTIGATIONS FOR DPR PREPRARATION
3.1
The following information / data of the town selected
are required:
3.1.1 Demographic data may be collected pertaining to the five preceding decades including current ward-wise data. The populations may be projected for the base and other relevant points of time using the census data, the potential for growth of population in each ward, scope of additional construction in the Master Plan and other relevant available data.
3.1.2 Economic, social and cultural information may be obtained from the gazetteer, plan documents prepared for submission to the State Planning Board or the State Government and other sources.
3.1.3 General topography and Land Use Pattern
3.1.4 Hydro-geological including geo-hydrological and Geotechnical
3.1.5 Storm Water
3.1.6 Water Supply Status of the town
3.1.7 Sewerage Supply Status of the town
3.1.8 Quantity and quality of waste water- sewage and sullage- in drains outfalling into the river
3.1.9 Municipal Solid Waste
3.1.10 Water quality upstream and down stream of the town and discharge of the water body
3.1.11 Flora and Fauna
3.1.12 Non Point Sources of Pollution
3.1.11.1 Dairies
3.1.11.2 Motor Garages
3.1.11.3 Cattle wallowing
3.1.11.4 Open area and bank side defecation
3.1.11.5 Dead body and carcass dumping
3.1.11.6 Indiscriminate dumping of garbage in nearby banks and open areas.
3.1.13 River front facilities– to improve aesthetics and reduce pollution / bank erosion.
3.1.14 Industrial effluent
3.1.15 Industrial Solid Waste:
3.1.16 Bio medical Waste & other hazardous waste
3.2 Additional Data Required For Coastal towns:
3.2.1 Tidal incursion and mangroves
3.2.2 Coast Line
3.2.3 Coastal Zone Management Plan
3.3 Additional Data Required For Towns On The Bank Of A Lake:
3.3.1 Bathymetry Of Lake
3.3.2 Water spread in different months and area encroached
3.3.3 Defining the Catchment Area
3.3.4 Land Use in the Catchment, identifying areas that yield sediment,
3.3.5 Discharge measurement of all inflows into and outflows from the lake,
3.3.6 Peak Flood Flow into the lake
3.3.7 Characterisation of the discharge flowing into the lake.
3.3.8 Water quality in selected sampling points chosen on the basis of sources of pollution of the lake. The water quality parameters chosen should include, in addition to the usual ones, sediment content by size, nutrient (Phosphorous and Nitrogen), pesticides if the return flow agricultural fields joins the streams feeding the lake and thermal profile i.e., temperature at different depths.
3.3.9 Sediment analysis particularly for Phosphorous and Nitrogen content
3.3.10 Hydro-biology of the lake:: Macrophytes, Animal communities, Zoo benthos, Zoo plankton.
3.4 Land Use, Contour, Drainage & Thematic Maps:
3.4.1 Satellite imagery can give the current land use map of the city and the catchment. The State Remote Sensing Agency, if it is in a position to do so, could be asked to prepare it using the most recent available imagery covering the area within municipal limits and extending 10 Kms beyond the municipal limits. It may also be asked to procure the maps prepared by the National Remote Sensing Agency (NRSA) under their Natural Resources Information System, the map of the municipal body and the Master Plan of the city should also be collected. However, if it is difficult or time consuming to get these inputs from the NRSA or the State Remote Sensing Agency, the map of the municipal body and the local Development Authority may be used.
3.4.2 The contour interval in the maps of the Survey of India (SOI) is large. Contour map of the city with at the most 5m contour interval should be obtained. If there is no such map a survey may have to be done particularly of the area where sewers have to be laid or pumping stations to be constructed.
3.4.3 Deviations in land use with respect to that shown in the Master Plan and encroachments should be indicated in the map.
3.4.4 Drainage map should be prepared if not already existing.
3.4.5 Tentative/provisional sites available for treatment plants, pumping stations and disposal works etc. should be identified and marked on the map.
3.4.6 Thematic maps may be prepared to the extent feasible and considered useful for the project.
3.5 Hydro-geological:
3.5.1 Meteorological data
3.5.2 Ground water depth and its seasonal fluctuation affecting construction, sewer infiltration and structural design,
3.5.3 Soil Bearing Capacity and type of Strata expected to be encountered in construction up to anticipated depths
3.6 Water Supply Status of the town:
3.6.1 Details of sources of discharge: quality, change in levels of underground and surface water supply sources, along with their locations on the city map.
3.6.2 Discharge available from each water supply source.
3.6.3 Ward-wise per capita water supply in lpcd- present and expected after works under constructions and planned are completed.
3.6.4 Plan showing water supply works, existing and under construction and future plans for augmentation of water supply in the town may be collected.
3.6.5 Brief description of water supply status of the town along with completion plans of the existing works
3.6.6 A copy of the water supply master plan/major estimates prepared earlier should be obtained.
3.7 Sewerage Status of the towns:
3.7.1 Ward-wise arrangements in the households for the disposal of toilet waste water.
3.7.1.1 Areas / streets covered with sewers
3.7.1.2 Areas / streets covered with Septic tanks and soakage pits discharging into street drains
3.7.2 Details of sewerage works in the town including completion plan of sewers, intermediate pumping stations, MPS, rising mains, STPs, showing diameters/lengths/gradients of sewers, levels, capacities, duties of pumping plants etc.
3.7.3 Out falls and drains / Sewers leading to the outfalls should be plotted on a drainage map of the towns.
3.7.4 A copy of the sewerage master plan / major DPRs prepared earlier.
3.8 Domestic
pollution:
3.8.1 No. of drains carrying the domestic sewerage, polluting the water body
3.8.2 Actual field survey to be conducted, for at least one month during dry weather to assess pollution load quantitatively and qualitatively. Actual present flows to be measured at the point of outfall into the water body. The pollutants, BOD, COD, Nitrogen, Phosphorous, Chlorides, Ph, temperature, colour, odour, total suspended solids, volatile suspended solids and faecal coliforms are also to be measured. The sample should be flow proportional and composited taken once a week for diurnal variation on hourly basis. For this purpose, considering a four week months, three samples to be taken on week days, whereas the fourth sample to be taken on an off day i.e. Sunday.
3.9 Storm
Water:
3.9.1 Strom water drains may be marked on the city plan.
3.9.2 Catchment areas of each nala to be marked on the city map showing ground levels, so that populations contributing wastewater to the nala could be ascertained.
3.10 Municipal
Solid Waste (MSW)
3.10.1 The survey and investigation for MSW may be done in accordance with the guidelines given as Annexure III
3.11 Water
quality and discharge of the water body:
3.11.1 Collect data about the quantity of flow/discharge from the CWC or the Deptt. Of Irrigation for as long a period as it is available.
3.11.2 Water quality -- BOD, COD, Ph, Temperature, Suspended Sediment, Heavy metals, Pesticides - - of the water body and its identified tributaries the stretches of the river within the limits of the town, upstream and downstream of the town concerned for a period of 10 years or for such period as the data is available, to be obtained from the records of SPCB, CPCB and CWC.
3.12 Flora
and Fauna:
3.12.1 Data to be obtained from the Botanical Survey Of India, Zoological Survey Of India, State Pollution Control Board / Central Pollution Control Board and (local University in case any research has been done).
3.12.2 Information on endangered and rare flora and fauna may be obtained. Endangered flora and fauna may need protection by way of restoration / conservation programme.
3.12.3 In case this information is not available or will take a long time to obtain, the DPR should not be held back and submitted without this information. The information should be collected later.
3.13
Coastal
Towns:
3.13.1 Water quality and discharge in case of coastal towns.
3.13.2 Additional data relating to tidal incursion and mangroves to be collected.
3.14
Non
Point Sources of Pollutions:
3.14.1 Dairies
3.14.1.1 Quantification of dairy waste
3.14.1.2 Present locations and disposal points to be marked on the city plan
3.14.1.3 Present treatment methods being employed
3.14.2 Dhobighats
3.14.2.1 Nos., locations to be marked on the city plan
3.14.2.2 Number of dhobis in each ghat,
3.14.2.3 Clothes washed and
3.14.3 Sites
reserved in the master plan for location of dairies and dhobi ghats
3.14.4 Motor
Garages
3.14.4.1 number and their locations on the city map
3.14.4.2 quantification of the washing from the garages
3.14.4.3 average no. of vehicles being washed per day
3.14.4.4 disposal sites of washing may be marked on the city map
3.14.4.5 sites reserved for the activity in the Master Plan
3.14.5 Cattle
wallowing
3.14.5.1 Locations of cattle wallowing
3.14.5.2 Number of Cattle wallowing &
3.14.6 Carcass
Disposal
3.14.6.1 Locations of carcass disposal
3.14.6.2 Number of carcasses disposed of per day
3.14.6.3 Sites reserved for carcass disposal in the master plan
3.14.7 Low
cost sanitation
3.14.7.1 Identification and marking on map of open spaces being used for open defecation
3.14.7.2 A survey to estimate the number of persons using each such space per day.
3.14.7.3 Location of community latrines in the city and the number of seats in each site.
3.14.7.4 Estimate of number of dwelling units in the city which do not have a latrine.
3.14.7.5 No. of dwelling units in the city which have only the dry pit latrine.
3.14.7.6 Details of activities already taken up under low cost sanitation programme of the Social Welfare Department and other state agencies
3.14.7.7 Identification of places where community toilets need to be set up, including the number of seats at each location. One seat can be assumed to cover 50 persons.
3.14.8 Crematoria:
3.14.8.1 Wood based-their number-show locations on the city map
3.14.8.2 Electric- their number – show location on the city map
3.14.8.3 Others- their number- show location on the city map
3.14.8.4 The number of bodies being burnt at each burning ghat during the last five years may be collected.
3.14.8.5 If under GAP or the NRAP, electric and wood based crematoria have been set up in the state, before deciding about the number and location of further crematoria to be constructed, the performance and acceptance of different type of crematoria may be ascertained.
3.14.8.6 Identification of places where additional crematoria need to be set up, including the number required.
3.14.9
River front facilities:
3.14.9.1 Identification of river ghats being used for bathing.
3.14.9.2 Identification of improvements required in bathing ghats.
3.14.9.3 Identification of new ghats to be constructed.
3.14.10 Plantation:
The plantation work may be planned in accordance with the guidelines given as Annexure IV
3.15 Industrial
Pollution Including Hazardous And Toxic Waste
3.15.1 The responsibility of ensuring that the industrial waste is safely disposed of in accordance with law is that of the respective industrial unit. The control and monitoring of pollution from industrial wastes is the responsibility of the State Pollution Control Board. The State Pollution Control Board is to ensure that the generators of industrial waste dispose it of, as prescribed in law and that the standards prescribed are observed. The SPCB may be asked to furnish the following information:
3.15.1.1 The number of industrial units in different wards and industrial areas.
3.15.1.2 Grossly polluting units-number, quantity & quality of solid waste
3.15.1.3 The points where the industrial, hazardous and bio-medical wastes are treated.
3.15.1.4 The points where the industrial, hazardous and bio-medical wastes are disposed of.
3.15.1.5 The points where the industrial, hazardous and bio-medical wastes are being mixed with the municipal wastes- effluents in sewers, solid waste in MSW. The points should be shown in the city map.
3.15.1.6 Its quantity and quality at those points should also be obtained. The information- quantity and quality- about different types of wastes such as MSW, industrial hazardous and biomedical should be obtained in disaggregated from separately for liquid and solid.
3.15.1.7 Existing arrangement for handling and treatment of Toxic, Hazardous, bio-medical/hospital wastes be indicated.
3.15.1.8 Number of hospitals, nursing homes and other units generating bio-medical waste. They may be plotted on the map showing land utilization.
3.15.1.9 Indicate sites reserved for treatment of bio-medical waste in the master plan.
3.15.2 The SPCB may be requested to review its performance and resources and if there is need, prepare a plan to enhance its capacity to ensure effective control and management of pollution in the town/city where the conservation measures are proposed.
CHAPTER
IV: DESIGN OF SYSTEM AND COMPONENTS
4.1 Type of Schemes: The system to improve the environment of the city may consist of sub-systems or schemes that relate to
4.1.1 Sewage collection, treatment, re-use / disposal
4.1.2 Low cost sanitation
4.1.3 Crematoria
4.1.4 Other non point sources of pollution
4.1.5 River Front Development Works
4.1.6 Watershed/Catchment Treatment:
4.1.7 Municipal Solid Waste (MSW)
4.1.8 Bio- medical waste
4.1.9 Human Resources Development
4.1.10 Institutional Strengthening
4.2
System Design:
4.2.1 Objective: The DPR should be prepared to achieve clearly spelt objective in terms of abatement of pollution from various sources of pollution and of environment improvement. There should be performance parameters of each components and the system as a whole so that the effectiveness can be monitored and evaluated.
4.2.2 Alternative System: Feasible alternative systems, keeping in view the existing infrastructure in the town should be prepared.
4.2.3 Sub-system alternatives for major components such as Sewage and MSW should include the alternatives of Centralised Systems and Decentralised systems.
4.2.4 Techno economic evaluation should be carried out on life cycle analysis of major components. This analysis should include capitalized annual O & M costs less revenue from resource recovery, recycling, by-product utilization. Interest on the Net Present Values (NPV) of the alternative systems considered. Ease of O & M, time required to construct and achieve the desired project objectives & costs of mitigation of any adverse environmental impacts to be loaded on the costs assigned for the alternatives., human, physical, electrical and other forms of energy, other pros and cons, reliability and long term sustainability should also be given appropriate weightages. On such an evaluation, the best option should be selected.
4.2.4.1 The summary of the above analysis shall form an important component of the draft DPR for public consultation before finalisation.
4.3
Design Criteria:
4.3.1
Sewage
4.3.1.1 It is not desirable for a town with piped water supply and flushing system to discharge the sewage from the dwelling unit directly in to street drain. If such a situation exists in a town or some of its parts alternatives for good sanitation including low cost sanitation should be worked out and what ever is practically feasible should be a part of the plan.
4.3.1.2 Sewers, sewage pumping stations and Sewage Treatment Plants proposed under river action plan would ultimately become a part of the town’s sewerage and sewage treatment facility. This aspect should be kept in mind while planning the project so that these works when executed in the town under town’s sewerage scheme match with the facilities built under river action plan.
4.3.2
Design Periods
Base year—The year of expected commissioning of the project shall be taken as the base year for design of various components of the projects. Design periods of various components may be adopted as under:
Table: Design Periods For Various
Components of The Project
|
S.No. |
Component |
Design Period from base
year |
Clarification |
|
1 |
Land acquisition |
30 |
Land will be required to add STPs. Accordingly, land should be acquired |
|
2 |
Sewer system |
30 |
|
|
3 |
SPS – civil works |
30 |
Cost of civil works is economical for full design period. |
|
4 |
Pumps |
15 |
Considering modular approach |
|
5 |
STP |
10 |
Construction may be done with a modular approach in a phased manner as the population grows. |
|
6 |
Rising mains |
30 |
In case of low velocities, dual rising mains to be examined |
|
7 |
Effluent disposal |
30 |
Provision of design capacities in the initial stages itself is economical. |
|
8 |
LCS |
|
Required as of base year |
|
9 |
Crematoria |
|
Required as per assessment |
|
10 |
RFD |
|
Required as per assessment |
|
11 |
MSW |
|
Requirement as per assessment |
4.3.3
Design population
Design population is to be worked out for each zone on a critical appraisal of the latest demographic data and projected population in the city master plan. New colonies that may come up in future should also be catered for. It should be ensured that the laws require the colonizer to provide conveyance and treatment of all wastes before discharge in to municipal drain/sewer.
Due to paucity of financial resources, at present it is proposed to limit the conservation programme to towns having the census population of the year 2001 as 1 lac or more. However, in case of cultural, tourism or religious importance of a town having a lower population, it can be included if on certain occasions large floating population converges.
4.3.4
Sewers
Sewers shall be designed as per latest Manual on Sewerage and Sewage Treatment, issued by the Ministry of Urban Development, Govt. of India
4.3.5
Interception factor
Generally 80% of water supply is expected to reach sewers. However to have a correct assessment of the waste reaching sewers, actual flow measurements of major drains be carried out for over a month. After knowing the contributory population of the drains and water supply rate, sewage interception factor shall be worked out.
4.3.6
Interception works
Nala tapping works shall be constructed on the course of a Nala, so as to intercept the dry weather flow flowing through the nala, and divert it into the nearby sewer.
4.4
Sewage Pumping Stations
4.4.1 Preference may be given to submersible pumps wherever, feasible, they being cheaper and operation friendly.
4.4.2 Configuration of sewage pumps
|
Where rising main is long |
Peak flow/2 pumps Non peak flow pumps |
3 nos. 4 2 nos. |
|
Where rising main is short |
Peak flow/4 pumps |
5 nos. 1 standby |
4.5
Sewage Treatment Plants
4.5.1
Land for STPs
The provision of land for STPs including sewage pumping station may be made as follows:
|
S. No |
Process |
Land
required (acre/mld) |
|
1 |
Activated Sludge/ Trickling filter |
0.5 |
|
2 |
Aerated lagoon |
1.2 |
|
3 |
Stabilisation pond |
2.5 |
|
4 |
Agro-forestery (Karnal Technology) |
3.75 to 6.25 depending on the nature of soil |
|
5 |
U.A.S.B. |
0.42 |
Land provision is to be made for the ultimate requirements in case of STPs, SPS and SWM, but for the present requirement in case of crematoria, bating ghats etc.
|
S. No. |
Parameters |
For discharge on land |
For discharge into water |
||
|
1 |
BOD (mg/l) |
<100 |
<30 |
||
|
2 |
SS (mg/l) |
<200 |
<50 |
||
|
3 |
Faecal coliform |
Desirable |
Max. permissible |
Desirable |
Max. permissible |
|
1000 |
10000 |
1000 |
10000 |
||
4.6
Technology
Technology option should be based on the cost benefit analysis of various options to achieve the desired standards and the most economic one selected.
Possibility of utilizing bioremediation techniques for lake conservation shall be considered depending upon its feasibility.
4.7
Low cost sanitation: There may be schemes of the
Government of India and the State Governments both for supporting Community
Toilets and individual toilets. Those schemes should be integrated with the
schemes of town:
4.7.1
Community Toilets
4.7.1.1 Guidelines given as Annexure II may be followed in this regard.
4.8
Other non point sources of pollution
The components mentioned below should become a part of the integrated project of river cleaning.
4.8.1
River front development
Bathing facilities in shape of pucca or kutcha ghats exist near the banks of rivers. Due to lack of maintenance or otherwise, some of these facilities have become defunct and need renovation. At some places, the existing facilities are very much inadequate and need to be supplemented. The river may also need strengthening like bund renovation, new bund, stone pitching etc. In lakes there are places for rowing boats.
Provision of such renovation and new facilities shall be made in consultation with the state irrigation department and the district authorities.
4.8.2
Crematoria
Improved Wood based crematoria have been provided in a large number of towns under Ganga Action Plan on the plans developed by NRCD. These may be adopted and may be modified as per local conditions, availability of land and some other problems in the use of such crematoria constructed earlier were encountered.
Electric crematoria have also have been constructed at some placaes under Ganga Action Plan have faced the problem of power. These may, however, be provided in big towns, where the availability of power & trained staff for maintenance in ensured.
4.8.3
Storm water drains
Strom water drains carry sullage and sewage also where sewerage facilities are inadequate or where due to unsatisfactory O& M of the system, broken sewer lines discharge into drains. Nala tapping works shall be constructed on the course of nalas, so as to intercept the city weather flow through them, divert it to the sewer and prevent it from entering into the river or lake.
4.8.4
Catchment Treatment And Afforestation
The data that needs to be collected is already given in Chapter III. A study of this data will suggest the works, which need to be undertaken to prevent soil erosion, which finally flows in to the waterbody causing many problems. The types of works that may be required to be done include:
4.8.4.1
Vegetative or non structural works such as:
4.8.4.1.1 Silvipasture and agro-forestry
4.8.4.1.2 Pasture development,
4.8.4.1.3 Afforestation
4.8.4.1.4 Horticulture
4.8.4.1.5 Crop improvement
4.8.4.1.6 Trenching,
4.8.4.1.7 Demonstration
4.8.4.2
Engineering or Structural Measures:
4.8.4.2.1 Loose boulder check dam
4.8.4.2.2 Gabion Check dam
4.8.4.2.3 Contour stone wall
4.8.4.2.4 Stabilisation of degraded area
4.8.4.3
Training and Evaluation
4.8.4.4
Institutional Strengthening
4.8.4.5 Note: The above activities are required to be undertaken in a watershed in a rural setting. Since we are dealing with the catchment area of a town, the catchment is likely to be in the process of urbanization. The effort should be to take up works, which would check soil erosion from areas that are very prone to erosion. Vegetative works should be preferred. The adherence to the Master Plan in land use is important.
4.8.5
Solid Waste Management
The design and management of Municipal Solid Waste may be done in accordance with the guidelines given as Annexure III.
5.1 Operation and Maintenance in all its facets is the responsibility of the local body aided and supported by State government. A firm commitment will be given by the local body that it agrees to bear the entire cost of O & M. The State Government shall give an undertaking that it will ensure that assets are properly operated and maintained and any short fall in resources will be met by them. The agency for O & M of the assets created will also be clearly mentioned in the DPR.
5.2 It is necessary to accurately assess the financial and other resources required for effective and efficient O & M. The resources required and associated costs are:
5.2.1 Energy – Electricity and diesel to be used in standby Generating Set- to meet the contingency of electric failure.
5.2.2 Man Power,
5.2.3 Consumables
5.2.4 Inventory of Spares
5.2.5 Tools and Plants
5.2.6 Preventive maintenance
5.2.7 Repairs of civil, electrical and mechanical works
5.3 Research and Development
5.3.1 Monitoring
5.3.2 Evaluation
5.3.3 Other problem solving
5.4 The feasibility of involving private sector in O & M should be considered. In some states it has been found to be economical and effective.
5.5
A detailed plan for raising the resources for Operation
& Maintenance shall become part of the project proposal.
5.6 The operation and maintenance manual of the various plants, structures, labs, etc. should be prepared.
5.7 In case it is decided to carry out O & M departmentally, staff required for O & M of sewage pumping stations, STP etc. may be adopted as per Annex II.
5.8 Timely availability of land for the facilities & assured uninterrupted power supply for the electrical equipment shall be ensured for the chosen alternative system in consultation with local bodies.
5.9 Revenue generation estimate from the sale/use of by-products of the STPs, garbage utilization plants including recycling & resources recovery shall be a factor for prioritising the best alternative.
5.10
Resources Mobilisation For O & M
5.10.1 Resource Recovery,
5.10.1.1
Sale of treated
sewage for use in irrigation and industry
5.10.1.2
Sale of sludge
for agriculture
5.10.1.3
Composting of
organic portion of MSW by vermiculture and other methods,
5.10.1.4
Generation of
electricity in STPs,
5.10.1.5
Water and
sewage cess
5.10.1.6
Fair
assessment, levy and recovery of property tax
5.10.1.7
House
connection charges
5.10.1.8
Fines on
Polluters
5.10.1.9
Taxes from
pilgrim/tourist/floating population visiting the town
5.10.1.10
Undertaking
plantation on municipal lands
5.10.1.11
Other sources
of recovery
5.10.2
Government
Contribution: If adequate funds are not raised from ‘resource recovery’
mentioned above, the shortfall of the funds required for O & M should be
promised by the State Government.
CHAPTER
VI : PUBLIC AWARENESS. & PUBLIC PARTICIPATION:
6.1 In the light of experience gained in the implementation of development programmes since independence and particularly from the Ganga Action Plan, it is now recognised that programmes for conservation of water bodies and town improvement can succeed only if
6.1.1 the communities are aware that
6.1.1.1 there is need for conservation programme and that they will benefit from it.
6.1.1.2 There are costs involved in such programmes and part of the burden will have to be borne by them,
6.1.2 The communities are effectively involved in all the stages of the project cycle from conceptualisation, to preparation, to finalisation, to implementation and finally O & M.
6.2 Hence Public Awareness & Public Participation should be a front-end activity of the project unlike the present practice of it being the last priority.
6.3 The entire programme of conservation should be conceived, formulated, implemented, monitored and evaluated in close consultation with the stake holding communities following the approach of “Participatory Appraisal’.
6.4 Issues involved in the conservation of the water body need to be identified and the programme will need to focus on them. The objective of the Awareness Plan will be determined by the issues identified.
6.5 Agency that will plan, implement and coordinate the Awareness Campaign should be identified. With a view to focus on issues relating to protection and improvement and cleaning of rivers/lakes, a massive program of environment education and awareness is imperative. Centre and states may launch this campaign through a program of volunteers called NATIONAL GREEN VOLUNTEERS.
6.6 Detailed guidelines for Core and Non-core schemes are given as Annexure VI
CHAPTER
VII : HRD AND CAPACITY BUILDING
7.1 A project has to undergo through the following phase:
7.1.1 Project planning,
7.1.2 Project preparation
7.1.3 Project implementation,
7.1.4 Monitoring evaluation
7.2 It involves the following aspects
7.2.1 Scientific and technical
7.2.2 Social,
7.2.3 Financial & Economic,
7.2.4 Institutional
7.2.5 Administrative,
7.2.6 Legal
7.3
Successful
project management will need the manpower with diverse skills, physical
and financial resources to deal with all the aspects mentioned above in all the
phases of the project.
7.4
Human Resources
Development will deal with appropriate skill development in the organisations
involved in the planning, design and management of the project. The main
activities are listed below:
7.4.1 Identify training needs
7.4.2 Identify institutes where education/training can be organised.
7.4.3 Well staffed and equipped Engineering Institutions, which have an interest in the subject, may be asked to develop training modules. They should be involved on a long-term basis so that they develop expertise in the aspects of this programme. They should be involved in various aspects and activities of the programme.
CHAPTER VIII : PROJECT MANAGEMENT & INSTITUTIONAL ISSUES
8.1 Selection of mode of implementation. Of the three alternative modes of implementing the project in vogue, mentioned below, depending upon the circumstances prevailing, the mode should be selected. The DPR should mention why the specific mode has been chosen.
8.1.1 Departmental,
8.1.2 Project Management Agency
8.1.3 A combination of above
8.2
Institutional Issues:
8.2.1 In Conservation & Management there are a number of institutions dealing with activities including:
8.2.1.1 Policy, strategy and programme formulation and their implementation
8.2.1.2 Supply of services
8.2.1.3 Development,
8.2.1.4 Management,
8.2.1.5 Regulation and enforcement,
8.2.1.6 Coordination with national, state and local organisations.
8.2.2
Overlap in roles of a involved institutions:
8.2.2.1 The role of three bodies is very crucial. They are:
8.2.2.1.1 Municipality which is responsible for sanitation in the town,
8.2.2.1.2 City Development Authority which regulates the new colonies
8.2.2.1.3 State Pollution Control Board, which is responsible for ensuring compliance by industry of the standards, prescribed under the Environmental Protection Act for effluent, solid waste and air emissions.
8.2.2.2 Many times there is an overlap in the roles of several bodies with the result that the efficiency with which the function should be performed suffers. The state Government needs to resolve such overlaps. The role of each institution involved needs to be very clearly specified.
8.2.2.3 The institutions that are involved in the conservation programme of the town suffer from weaknesses. The DPR should identify such areas needing improvement.
9.1 The National River Conservation Authority (NRCA) has decided that the Financing pattern of schemes of the NRCD for the conservation of rivers and lakes will be as follows:-
9.1.1 Government of India (NRCD) to bear 70% of the project cost,
9.1.2 States and the local bodies to bear 30% of project cost of which Share of the public shall be a minimum of 10%.
9.1.3 O & M shall be a part of the project and the costs thereon shall be borne entirely by the state and the local bodies for which additional resources have to be demonstrably raised and committed to O & M.
9.1.4 The Local Bodies may raise loans from Financial Institutions such as HUDCO to contribute their share,
9.1.5 If for any reason such as delay, wrong design or estimation, omission of items, inflation etc., there is cost overrun in any project, the central share in the total cost will be limited to the ceiling amount approved by the CCEA. Balance, if any, is to be borne by the respective state Government. It is, therefore, necessary to prepare the DPR accurately after investigation and survey and taking all factors into account that can influence the cost of the project.
9.2 The State Governments should make all efforts to obtain larger plan allocations for such programmes.
9.3 The contribution of 10 % from the beneficiaries and stakeholders can be raised in one or more of the following forms.
9.3.1 additional development charges, water and sewage cess
9.3.2 fair assessment, levy and recovery of property tax
9.3.3 house connection charges
9.3.4 contribution from Development Funds of local MPs and MLAs
9.3.5 Fines on polluters
9.3.6 Taxes from pilgrim/tourist/floating population visiting the town
9.3.7 Donation from industry, business associations, voluntary agencies such as Rotary and Lion’s clubs and philanthropists.
9.3.8 Any other mode.
9.4 It will be seen that the Integrated Project will include cost elements, many of which will not be financed by the NRCD. The NRCD will clarify which of the elements will be financed by it and which ones not financed by it.
9.5 The DPR should state how the finance would be raised for those items in the DPR that will not be considered for financing by the NRCD.
CHAPTER X : MONITORING & EVALUATION
10.1
The
improvements in the water body and the environment of the town will have to be
monitored and evaluated after the implementation of the project.
10.2
The
conservation Programme is expected to yield results, which should be quantified
in the DPR to the extent, it is feasible to do so. Other results will have to
be qualitative.
10.3
Depending upon
the items of works taken up, a programmes of monitoring should be developed and
it should be assigned to a well-equipped laboratory in a University or the
SPCB. The expenses on the monitoring should be estimated and should form a part
of the funds required for O & M.
10.4
After the project
has been fully implemented, it is necessary to evaluate the project. Funds
should be provided for this purpose also.
CHAPTER
XI : COST ESTIMATES AND GENERAL REQUIREMENTS OF DPRS
11.1 COST
ESTIMATES:
11.1.1 Based on survey and investigation, data collection and design criteria, detailed estimates may be prepared, under the following subheads:
11.1.1.1 Land Acquisition
11.1.1.2 Interception & Diversion Including Internal Sewers
11.1.1.3 Sewage Treatment
11.1.1.4 Low cost sanitation
11.1.1.5 Crematoria
11.1.1.6 Abatement of Non Point Sources of Pollution
11.1.1.7 River Front Development Works
11.1.1.8 Watershed / Catchment Treatment and Plantation
11.1.1.9 Municipal Solid & Biomedical Waste management
11.1.1.10 Tools & Plant For The Maintenance of the Works
11.1.1.11 Operation & Maintenance
11.1.1.12 Monitoring & Evaluation
11.1.1.13 Any other identified scheme
11.1.1.14 Awareness and Public Participation
11.1.1.15 Human Resources Development
11.1.1.16 Institutional Development & Strengthening
11.2 DPRs – General Requirements
11.2.1 Earlier Project Feasibility Reports were entertained along with proposals for works under the National River Conservation Plan. However, the experience has been that actual costs have been very different from those sanctioned on the basis of PFRs. It has now been decided that hence forth only DPRs will be entertained.
11.2.2 DPRs shall be a comprehensive document prepared in accordance with these guidelines. They should contain all relevant information, collected and surveyed data, designs of system and components, justifying chosen system and scheme, components thereof and establishing that the cost shown is optimal, specifications, drawings. They should be documents worked out to details to invite tenders.
11.2.3 If feasible, the spatial data collected should be put in GIS format.
11.2.4 There should be separate volumes for major items such as I & D, STPs, LCS etc. In case I & D scheme becomes too large, DPRs may be prepared zone wise. Intermediate pumping stations, if any shall form part of I & D scheme. The main pumping station, which is the last pumping station before STP, shall form part of STP scheme.
11.2.5 DPRs shall be prepared on computer. Along with hard copies, a copy of the floppy/ disc shall be submitted to NRCD.
11.2.6 Salient features of the DPR should be given at the beginning of the DPR to have an idea of the DPR at a glance.
11.2.7 Schedule for submission, approval, implementation and completion shall be detailed.
11.2.8 Scheme-wise quarterly fund requirements from the local body, State and Central Government should also be given.
11.2.9 Bar charts /CPM / PERT networks based on realistic time schedule of completion of different activities shall be enclosed with the DPRs, indicating the work breakdown structures details and critical path for large schemes.
11.2.10 CPHEEO/ CPWD/ ISS/ Local PWD specifications, whichever applicable, may be followed for construction of works.
11.2.11 Cost estimates to be based on current local schedule of rates for standard items of works & market rates for proprietary equipment.
11.2.12 Necessary escalation in costs due to inflation during project implementation period shall be incorporated on a justified rationale.
11.2.13 Centage charges: A provision of 8% would be allowed towards project preparation, contingency, supervision, etc. on base cost estimate. In the case of states where the centage on works is higher that 8%, the balance will be provided by the State Governments. These charges will not be applicable on the cost of land, taxes etc. if any
11.3
Check List:
The checklist given in Annexure VII contains
important steps that should be taken in prescribing the DPR. It may be filled
up and enclosed with the DPR.
11.4
Completion Reports:
It should be borne is mind that after the
completion of the works, completion reports will have to be submitted in the
formats given in Annexure VIII.
ANNEXURE I
RESOLUTIONS ADOPTED AT THE XTH MEETING OF
THE
NRCA – MARCH’2001 – PM IN CHAIR.
1. While river cleaning would need to be given a much higher priority, it is also essential that resources are not spread thinly. The focus, therefore, has to be on large towns, which are gross polluters,
2. In case of works already completed, assets need to be maintained and also continuously operated /utilised for which funds must be earmarked by the States. The states/ UTs must meet the O & M costs which on an average is around 5% of the capital cost.
3. A holistic and integrated approach shall be adopted by addressing not only river pollution but also other components like internal sewerage, solid waste disposal, low cost toilets etc.
4. The cost of works shall be shared between the central and states/local bodies, public on 70: 30 basis. The public shall contribute not less that 10% of the cost.
5. A detailed plan for recovery/ operation maintenance cost shall become part-of the project proposal in future.
6. Because of delay in implementation, there is a cost overrun in many schemes. The central share in the total cost will be limited to the ceiling amount approved by the CCEA. Balance, if any, is to be borne by the respective State Government.
7. Approved works must be completed first and where states/UTs have not been responsive enough and such works have been pending for more than two years because of non-action by states, a committee of secretaries consisting of Secretary ministry of environment & Forests, secretary finance, secretary planning Commission and chief secretary of the concerned state shall review the necessity of such schemes.
8. National lake conservation plan shall receive the same priority as the rivers.
9. Mobilisation of resources/funds will need special attention. Plan outlays would need to be enhanced substantially so that gap between fund requirements and outlay is bridged
10. Coastal towns would get special attention because it has been observed that sewage, solid waste, bio-medical waste and the like are dumped into sea. Prioritisation of coastal towns for taking up such works may be done from the angle of mangroves, promotion of eco-tourism, cultural and religious importance of the place and like.
11. With a view to focus on issues relating to protection and improvement and cleaning of rivers/lakes, a massive program of environment education and awareness is imperative. Central and states to launch this campaign through a programme of volunteers called “National Green Volunteers”.
ANNEXURE II
GUIDELINES FOR
PREPARATION OF SCHEMES OF LOW
COST SANITATION
(LCS)
1.
Community Toilets
·
In localities
where all individual dwelling units do not have their own toilets, community
toilets should be constructed. 10,15 and 20 seated toilets may be provided
depending upon the space and number of users.
·
Separate toilets complexes for men and women may be
considered.
·
Plinth area for these types of LCS units will be as
under:
|
S.NO. |
Type |
Maximum Plinth Area (sq.m.) |
|
1 |
10 seated |
80 |
|
2 |
15 seated |
125 |
|
3 |
20 seated |
150 |
The above areas are proposed keeping in view
the facility available for cleanliness, hygienic condition and environment and
user friendly.
2.
Sizes
For all types of LCS blocks,
two urinal for gents, two bathrooms one each for ladies and gents, one guardroom
and one counter shall be provided.
The sizes may be adopted as under with a tolerance of 10%
|
S. NO. |
Component |
Size (sq.m.) |
|
1 |
Bath room |
1.2 x 1.5 |
|
2 |
Guard room |
3.0 x 3.0 |
|
3 |
Counter |
3.0 x 1.2 |
3.
WC Enclosure
Its size shall be 0.9 x 1.2 m (tolerance of
10%). Doorframes could be fabricated out of pressed MS/ GI sheet or other
cheaper material, which is locally available with size 0.75 x 1.8 m. Brass
material shall not be used at any place.
Ordinary
glazed tiles or mosaic may be provided upto 1 metre height skriting. Floor
shall be of P.C.C. Shutter of the door shall be 1.5 feet less than the height
of the frame. In the rear side, precast RCC jali may be used for proper
vantilation.
4.
Water Supply
WCs shall be pour flush type. Water tap may
be provided in WC enclosure keeping in view the local requirement/ practice.
The taps in WCs & Bathrooms shall be self-closing type of CI material.
Overhead storage tank should be provided. The capacities of the OHT shall be as
follows:
|
S.No. |
Type |
Maximum Capacity |
|
1 |
10 seater |
4000 litres |
|
2 |
15 seater |
6000 litres |
|
3 |
20 seater |
8000 litres |
5.
Disposal System
The LCS units shall be provided with septic
tank followed by soakpit. These units shall be properly designed. However, if
the sewer line exists near such units, it should be directly connected to the
sewer line.
If the sewer line is situated away from the
LCS unit, a comparison between the cost of sewer line and septic tank etc.
should be carried out to adopt the
least cost solution.
6.
Bio Gas
At one or two locations, biogas generation
package for 20 seater toilets shall be prepared and tried for revenue
generation.
7.
Norm for Usage Of
Toilets
As the norm for usage of such toilets is 50
persons per seat, therefore, the number of users for 10-seater complex shall be
500.
The location of toilet complexes should be
identified after proper investigation and survey & with the involvement of
the beneficiaries, so that the availability of the number of users is ensured
for full utilisation of the facility.
In order to keep the toilets in proper
hygienic conditions, agencies for operation and maintenance, should be
carefully identified for their sustainability. Revenue generation for operation
and maintenance of the toilet complexes shall be an integral part of the
scheme.
10.
Individual toilets
The owners of Dwelling units not owning
toilets should be encouraged to construct their own toilets. For the poor there
may be state schemes of subsidy and loan. The poor should be helped to avail
themselves of such schemes. Institutional finance may be arranged for the
others.
11.
Recommendatory
nature of LCS Guide Lines:
These guidelines are recommendatory in
nature. Actual designs may vary keeping in view local conditions.
ANNEXURE III
GUIDELINES FOR PREPARATION OF SCHEMES OF SOLID WASTE
MANAGEMENT UNDER RIVER PLAN
The proposal should contain the following information / data for the analysis of existing facilities:
1
GARBAGAE DATA:
Per Capita generation, quality (physical and analysis), zone wise quantity generated in respect of Municipal, Industrial/Hospital and Hazardous waste per day, present mode of dumping (burning/scientific method), problem in sewer/drain due to chokage etc. have to be elaborated.
2
HANDLING FACILITY:
Existing mode of collection, transportation and disposal of solid waste and effectiveness in terms of equipment, manpower etc. has to be elaborated. The location of collection and disposal sites has to be shown on map.
3
FUNDING:
Source of fund/assistance received by the Municipality for meeting the cost of personnel, fuels and other operation and maintenance cost being incurred may be indicated.
4
EFFICACY AND SUSTAINABILITY:
Whether the present system is efficacious, sustainable and cost effective may be elaborated.
5
RECYCLING AND WASTE MINIMISATION:
Does the existing system have provision of minimising waste at source, segregation of inert material, recycling, treatment, and scientific disposal & energy and revenue generation? If so, are their any plans notified by the Authority and steps taken thereof? This has to be elaborated.
6
HAZARDOUS AND TOXIC WASTE MANAGMENT:
Existing arrangement for handling of Toxic and Hazardous/Hospital waste, if any, has also to be indicated. It may be also noted that wastes of these kinds have to be tackled by enforcing laws and Acts and would not form part of solid waste management scheme.
B.
PROPOSED SYSTEM :
1.
Quantification :
Quantification of solid waste generation
corresponding to design year has to be supported with presents status in terms
of per capita generation and other sources if anticipated any. The exercise has
to be carried out zone wise.
2.
Quality/Analysis of
Wastes:
Composition of waste like plastic, street
rubble, construction waste, glass, metal, wood stone etc. and compostable
material in terms of percentage has to mentioned. Report of High Power
Committee, Planning Commission, GOI may be referred for this. Analysis for
obtaining calorific value of garbage has also to be done. This is essential for
planning of utilisation of solid waste on mass scale.
3.
Collection,
Transportation and Disposal:
Justification for proposing various
movable equipments, proposed number & capacity and carrying capacity per
day for collection and transportation have to be described. Efforts have to be
made to minimise such number of mechanical equipments for optimisation of
recurring cost. For this, the existing facilities to handle the waste should be
taken into account and only additional facilities necessary to be included in
the proposal. Methods of disposal of various kinds of constituent materials of
solid waste i.e., compostable and biodegradable materials, inert materials etc.
have to be separately proposed and described.
4.
Cost Economy and
Planning:
While designing the management system,
cost economy with regard to decentralised planning of disposal, minimisation of
waste at source, economically viable method for collection, transportation and
disposal have to the followed and justified in the report.
5.
Scientific Disposal
and Treatment:
The method of disposal/treatment of
solid waste must be scientific and environment friendly. Proper design of
landfill site has to be done to avoid any detrimental impact on the environment
and locality. Leachate from solid waste has also to be treated if so warranted.
Vermicasting, Composting, Palletisation etc. may be explored for treatment of
waste.
6.
Optimisation of
Transportation Cost:
Minimal transportation cost has to be
achieved by using transportation model for entire town. This will reduce the
burden of vehicles required for transportation of Garbage. Model followed by
Ahmadabad municipality may be studied and if found feasible, may be replicated.
7
Resources Recovery:
Provision may be made for resource recovery
by ways of recycling, energy generation, sale of manure and reclaiming the
dumping site. A note on this delineating feasibility, planning and marketing
strategy has to be inserted in the DPR.
8
Budget for
Operation and Maintenance:
In view of the fact the management system has
to be made dynamic with constant financial support from the State Govt.,
estimated annual recurring expenditure on personnel, fuel, repair and
maintenance cost etc. and source of funding, annual budget provision etc. for
at least five years from the commissioning of the scheme have to be worked out.
Income generation plan if any proposed by the authority may also be indicated
together with its viability. Creating facility should not become liability for
the municipality at a later date due to paucity of fund. Therefore this aspect
is mandatory and integral part of scheme.
9
Privatization:
In order to have efficient management system,
the entire system or a part of it may be entrusted upon private parties. This
could be done keeping in view the services of the existing staff. A report on
this has to be submitted after proper study. Attempts should at least be made
to privatise transportation of waste to the extent possible.
10
Assistance from
State Govt.
Whether the concerned municipality or local
Body has referred the problem or inadequacy of solid waste handling to the
Deptt. Of Urban development of the state govt. at any point of time seeking
financial and technical assistance and the outcome thereof.
11 Land Cost
Provision for cost of land for filling purpose may be included in the
estimate.
JUSTIFICATION OF SCHEME UNDER RIVER CONSTRUCTION PLAN AND OVER ALL PLAN:
The state Government/ implementing agency has
to furnish an over all plan of management of solid waste of the entire
town/city. Funds will be considered for relevant portion of the scheme related
to pollution abatement of river only.
Establish link of pollution of river with
proposed solid waste management scheme and give justification for its inclusion
as pollution abatement scheme. It has also to be indicated that how much of the
total scheme is relevant for taking up under River conservation plan. The rest
will eventually be the responsibility of the state Government/local authority.
1.1 To
improve the aesthetics of the project area
1.2 To
check riverbank erosion.
1.3 In the case of lakes to check erosion of the catchment and
inflow of sediment into the lake
2.1
Campuses of
STPs, Pumping Stations, Lifting Stations, along Effluent Channels, Pathways and
areas around Crematoria, areas around Bathing Ghats and Low Cost Sanitation
Facilities etc.
2.2
River banks
under the project area.
2.3
In the case of
lakes erosion prone areas in the catchment
2.4
A map of the
areas proposed to be taken up under the project will form a part of the project
document
3.1
These are
essentially to be avenue / aesthetic plantations and hence suitable local
flowering tree species in consultation with local people and with active
participation of NGOs who are working in that area may be selected.
3.2
In case of
plantations around STPs, Pumping Stations and along Effluent Channels, tall
plants having dense foliage shall be planted.
4.1
In the states,
to take up plantation is the responsibility of the State Forest Department. As
they are expected to have the requisite expertise and infrastructure, they may
be given the first preference to take up works under these guidelines.
4.2
If the State
Forest Departments on account of their prior commitments is not in a position
to implement these works or the concerned State Governments take decisions
otherwise, these works can be assigned to alternative agencies.
5
Financial Norms For Plantation
5.1
Estimates to
include provisions for maintenance for a period of 3 years including the
planting year.
5.2
No barbed wire
fencing or expensive tree guards will be permissible unless proper
justification is given. Low cost vegetative fencing should be encouraged.
5.3
Employment of
watchmen for the purposes of protection will not be allowed.
5.4
Appropriate
mechanism must be evolved for maintenance and protection of the plantations
taken up under these guidelines by resorting to the concepts of social fencing
with the involvement of NGOs, Paryavaran Vahinis, Eco-clubs, Forest Protection
Committees, Panchayati Raj Institutions etc. This mechanism must be indicated
in DPR.
6 Records to be maintained
The implementing agency will be required to
meticulously maintain requisite documents like plantation registers including
treatment map, measurement books, accounts etc. It will also diligently
maintain every six months, the survival percentage of the plantations.
7 Evaluation
Works taken up will be monitored / evaluated
by experts to be selected from the panel maintained for the purpose in the
Ministry. Visit of these evaluators will take place once every year
(November-January) to each project and assessment of work will basically be
done with reference to the calendar of operations submitted along with the
project proposal.
ANNEXURE V
1. Sewage Pumping Stations
Staff Required
|
Installed Capacity 150-300 HP |
Installed Capacity 300-500 HP |
Installed
Capacity >500 HP |
|
J.E. |
½ |
1 |
1 |
|
Pump Mechanics |
1 |
1 ½ |
1 ½ |
|
Electricians |
1 |
1 |
1 |
|
Pump Operators |
1x3 |
1x3 |
1x3 |
|
Beldars |
1x2 |
1x3 |
2x3 |
|
Sweepers |
1x1 |
1x1 |
1x1 |
Staff Quarters
Required for Operating Staff |
|
|
|
|
Pump Operators |
Type B 1 |
Type B 1 |
Type B 1 |
|
Beldars |
Type A 1 |
Type A 1 |
Type A 2 |
|
Pump Mechanics |
|
|
Type B 1 |
|
Electricians |
|
|
Type B 1 |
Total
|
2 |
2 |
5 |
2.
Sewage
Treatment Plants (ASP / Biofiltration)
|
Staff |
Types of
staff Qts. |
10 mld |
40 mld |
80 mld |
120 mld |
|
||||
|
Quarters Required |
|
|
|
|
|
|
||||
|
Beldars |
A |
4 |
4 |
6 |
8 |
|
||||
|
Operators |
B |
2 |
4 |
4 |
6 |
|
||||
|
Electrician class 1 |
B |
1 |
1 |
1 |
1 |
|
||||
|
Pump mechanic/Fitters class 1 |
C |
- |
1 |
1 |
1 |
|
||||
|
J.E. |
C |
- |
1 |
1 |
1 |
|
||||
|
A.E. |
D |
- |
- |
1 |
1 |
|
||||
|
Operators (Power Plant) |
B |
- |
2 |
2 |
2 |
|
||||
|
Sub-total |
|
7 |
11+2 |
14+2 |
18+2 |
|
||||
|
Oxidation Pond |
|
|
|
|
|
|
||||
|
Beldars |
A |
2 |
2 |
|
|
|
||||
|
Aerated Lagoons |
|
|
|
|
|
|
||||
|
Beldars |
A |
2 |
2 |
|
|
|
||||
|
Operators |
B |
2 |
2 |
|
|
|
||||
|
UASB Treatment Plants |
|
|
|
|
|
|
||||
|
Operators |
B |
1+1 |
1+1 |
1+1 |
1+1 |
|
||||
Staff
|
Types of staff
Qts. |
10 mld |
40 mld |
80 mld |
120 mld |
|||||
|
Sweepers |
A |
1 |
1 |
1 |
1 |
|||||
|
Watchmen/Gatemen |
A |
1 |
1 |
1 |
1 |
|||||
|
Electrician cum Mechanic |
B |
1 |
1 |
1 |
1 |
|||||
|
Chemists*** |
B |
1 |
1 |
1 |
1 |
|||||
|
J.E.** |
C |
1 |
1 |
1 |
1 |
|||||
|
A.E.(Civil) |
D |
- |
1 |
1 |
1 |
|||||
|
EE(Civil) |
- |
- |
- |
- |
- |
|||||
Note: * Operators’ quarter for Power Package
** One J.E. would look after more UASB Plants in a town
*** One Chemist would look after more UASB Plants in a town with a single laboratory.
(Area as per CPWD norms)
|
Personnel |
Type |
Plinth Area |
|
Sweepers, Watchmen |
A |
34.20 sq.m. |
|
Operators, Electricians & Chemists |
B |
45.60 sq.m. |
|
J.Es. |
C |
62.70 sq.m. |
|
A.Es. |
D |
86.00 sq.m. |
Guide Lines For Staff Quarters
1. No staff quarters are necessary for the IPS and MPS, if the installed capacity is less than 150 HP.
2. The staffing pattern for STP has been taken as per the guidelines of the Expert Committee set up by NRCD for the above purpose.
3. Number and type of quarters for different capacities any types of treatment plants have been worked out taking into consideration the operating staff in shifts. Quarters have also been proposed for minimum maintenance staff in large pumping stations and STPs.
4. Only a few supervisory staff at large STPs are to be considered for staff quarters at the site of treatment plant.
5. The pay scales and type of accommodation are based as per norms laid down by the Ministry of Urban Development.
6. If the land is not available at the site of MPS for construction of staff quarters, these quarters can be constructed at the site of treatment plant.
7. Staff quarters are not to be treated as rent-free.
8. 20% of the operating staff in shifts is to be provided quarters in the vicinity of STP.
9. States can adopt their own eligibility norms for different categories of staff, provided the variations are not too large.
REQUIREMENT OF PERSONEEL FOR STPs
|
Designation |
Activated sludge
Process/UASB |
High Rate
Filtration |
Oxidation Ditch |
Oxidation Pond |
Aerated Lagoon |
|||||||||||||||
|
Ex Engineer (Project Manager) |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
- |
- |
- |
- |
- |
- |
|
AE(E&M)Asstt. Manager |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
|
AE(Civil)Astt. Manager |
- |
- |
- |
1 |
- |
- |
- |
1 |
- |
- |
- |
1 |
- |
- |
- |
- |
- |
- |
- |
1 |
|
JE(E&M)Junior Manager |
4 |
4 |
6 |
6 |
4 |
4 |
6 |
6 |
4 |
4 |
6 |
6 |
- |
- |
- |
- |
4 |
4 |
4 |
4 |
|
JE(Civil)Junior Manager |
- |
- |
1 |
2 |
- |
- |
1 |
2 |
1 |
1 |
1 |
2 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
2 |
|
Fitter(Mech)Ist Class |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
- |
- |
- |
- |
- |
- |
1 |
1 |
|
Electn, Ist class |
1 |
1 |
2 |
3 |
1 |
1 |
1 |
2 |
1 |
1 |
2 |
2 |
- |
- |
- |
- |
1 |
1 |
2 |
2 |
|
Fitter, 2nd class |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
|
Electn, 2nd class |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
1 |
1 |
1 |
1 |
1 |
1 |
2 |
2 |
|
Gardener |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
|
Driver |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
- |
- |
- |
- |
1 |
1 |
|
Cleaner |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
- |
- |
- |
- |
1 |
1 |
|
Jr. Accountant |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
|
UDC, Senior Astt. |
1 |
1 |
1 |
2 |
1 |
1 |
1 |
2 |
1 |
1 |
1 |
2 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
|
LDC/Typist Junior Astt. |
1 |
1 |
2 |
3 |
1 |
1 |
2 |
3 |
1 |
1 |
2 |
3 |
1 |
1 |
2 |
2 |
1 |
1 |
1 |
2 |
|
Peon |
1 |
1 |
2 |
3 |
1 |
1 |
2 |
3 |
1 |
1 |
2 |
3 |
- |
- |
1 |
1 |
1 |
1 |
1 |
2 |
|
Jr. Steno |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
- |
- |
- |
- |
- |
- |
|
Chemist |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
- |
- |
- |
- |
- |
- |
|
Asst. Chemist |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
- |
- |
- |
- |
1 |
1 |
|
Lab Astt. |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
|
Lab Attendant. |
1 |
2 |
2 |
2 |
1 |
2 |
2 |
2 |
1 |
2 |
2 |
2 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
|
Sweeper |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
1 |
1 |
2 |
2 |
|
Welder cum Balcksmith |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
- |
- |
- |
- |
- |
- |
|
Operators |
12 |
16 |
19 |
19 |
12 |
16 |
19 |
19 |
8 |
8 |
12 |
12 |
- |
- |
1 |
1 |
4 |
4 |
4 |
4 |
|
Labour (Beldars) |
28 |
44 |
54 |
73 |
28 |
44 |
53 |
72 |
21 |
28 |
48 |
52 |
11 |
20 |
36 |
50 |
10 |
14 |
27 |
34 |
ANNEXURE VI
GUIDELINES FOR
PUBLIC AWARENESS AND PUBLIC PARTICIPATION IN
NATIONAL RIVER
ACTION PLAN SCHEMES OF THE MINISTRY OF
ENVIRONMENT AND
FORESTS
1.
INTRODUCTION:
It appears to be a turning point in the philosophy and programmes of NRCD to think loudly in terms of the importance and need of community awareness and community action for ensuring the desired success to the non-core schemes of National River Conservation Programme through people’s participation. Unfortunately, even after a huge expenditure of thousands of millions of rupees, the out come of most of the activities undertaken to implement the ambitious projects like Ganga and Yamuna Action Plan and now National River Conservation Programme has been far below the expectation of the nation. There may be different opinions of the casual factors responsible for such alarming situation. The fact however, remains that much of the disappointing experience or poor performance of the projects like these can be attributed to the fact that from the very beginning there has not been any sincere or systematic effort to involve community at any stage of the execution of the programme. The obvious result is that the general public for whom the whole exercise was planned so ambitiously always remained to be an indifferent on-looker. At times, the target beneficiaries contributed to the problem of river pollution because of number of ‘human factors’. Although, they did not do it deliberately, yet the fact remains that it was done because of the lack of proper awareness about the casual factors of river pollutions and also the dangers of the hazards of polluted river water, which is gradually turning into a slow poison. Hardly any meaningful effort has even been made to motivate the process to contribute their share to the efforts of keeping rivers off pollution. For example, number of hardware provisions were made to check the “human casual factors” of river pollution but there was rarely any systematic effort to educate the masses on the recommended practices for the proper use and maintenance of such facilities of toilet complexes, bathing ghats, crematoria, river bank structures, sewage systems, etc. It is shocking to note that not even ten percent of the total budgetary provision of NRCP has ever been made on software aspects. The outcome has been the same as could be expected under such conditions. It is heartening to note that NRCD has now realised the importance of community awareness/people’s participation in general and software components of the programme in particular. It may be pertinent to point out that the working of NRCP cannot be improved unless at least twenty five percent of budget provision is made for software programme. Some of the measures, which may be suggested to create meaningful community awareness and ensure fruitful participation of the masses for the success of National River Action Plan, are detailed below:
2.
GUIDELINES
FOR NON-CORE SCHEMES
VIZ LOW-COST TOILET
ELECTRIC/WOOD BASED CREMATORIA, BATHING GHATS, PLANTATION
ACTIVITIES, SOLID WASTE MANAGEMENT, ETC.
2.1 Target Groups
2.1.1 Local influential/Community leaders,
2.1.2 Local NGOs,
2.1.3 School teachers and students,
2.1.4 Elite groups and organisations like Rotary Club, Lions club, Associations and forums of writers and artists, etc.,
2.1.5 Religious leaders and priests,
2.1.6 Representatives of Industry and Commerce,
2.1.7 Leaders of trade unions and organisations like safai karamchari sanghs,
2.1.8 Leaders of teachers and students associations,
2.1.9 Representatives of political parties including the elected office bearers and members of local bodies,
2.1.10 Members of legislative assemblies, legislative councils and parliament representative of the local constituencies,
2.1.11 Representatives of media viz. Editors/correspondents of local press and key functionaries of local radio and TV stations,
2.1.12 Grassroot level functionaries of Municipalities and state government departments like public health, forestry, Jal Nigam, PWD, etc.,
2.2 Action Points
for Community Awareness
2.2.1 Holding of locality wise meetings and group discussions with local influentials, Whereby the extent of river pollution, the related physical and human factors, the consequent health hazards and the possible remedial measures are highlighted through the talks and technical presentations by the experts and social workers (Action: Identified NGO of reputation).
2.2.2 Motivating local influentials to play a leading role in promoting environmental sanitation and community health, particularly prevention of river pollution (Action: Identified NGO of reputation).
2.2.3 Motivating and advising local NGOs to participate in outlining execution and follow up efforts of community action plans for ensuring a clean and healthy community life in general and protection of river water quality in particular (Action: Identified NGO of reputation).
2.2.4 Promoting schools as models of clean living and healthy environments and training school teachers and students as motivators and informal change agents for involving families and communities in clean river programmes in general and maintenance of toilets/bathing ghats/crematoria in particular (Action: Identified NGO with excellent track record of having rendered specialised services in the area).
2.2.5 Motivating school management programmes/events administrative and teaching faculty to organise special programmes for checking river pollution and plantation of trees on the river banks (Action: Identified NGO and the functionaries of the Department of Forestry).
2.2.6 Motivate the local influentials i.e. leading businessmen, industrialists, office bearers of elite clubs like Rotary, Lions, Junior chamber of Commerce, local chapters of FICCI/CII, to undertake or sponsor such activities as solid and liquid waste management services through an effective strategy of public-private partnership for improving sanitation conditions of the towns located at river banks and also for joint efforts for controlling river pollution from industrial effluents. They can be fruitfully motivated to sponsor the plantations on river banks and adopting a certain planted area for protection and preservation (Action: NGO of reputation and duly motivated group of local influentials).
2.2.7 Awaken, educate, organise and motivate religious leaders and priests to participate actively in river pollution control through such efforts as educating the masses, checking the dumping of temple waste on the river bank and throwing of half burnt or unburnt dead bodies into the river (Action: NGO of reputation).
2.2.8 Motivate the office bearers of trade unions and other professional organisations like the teachers and students associated to win public support for their cause by rendering some fruitful service to the society. While doing so they may give highest priority to community health promotional measures like river pollution control and conservation of the quality of river water (Action: NGO of reputation).
2.2.9 Motivate local MLAs and MPs and leaders of political parties to participate actively in the promotional efforts of community involvement for protecting river against the hazards of pollution-an effort, which shall pay them abundantly through the building of positive public opinions. They should also be motivated to form local level all party organisations/ forums to promote the measures of river pollution control. In addition, they should be motivated to take keen interest in the proper utilisation of the funds provided for river pollution. In addition, they should be persuaded to play effective liaison between the government and the people to ensure the timely completion of different programmes and activities undertaken by the Directorate of National River Conservation Programme (Action: NGO having a sound background of linkages with the legislative and political leaders).
2.2.10 Motivate leading persons representing local press and electronic media infact, they need to be properly educated and encouraged to be conscious of their social commitment and social obligations. They should also be convinced that socially conscious media shall always be aptly recognised and enormously rewarded through the creation of a sound base of enlightened clientele group which in the long run will help them through the image building process. Accordingly, the editors and correspondents of local press, the officers and key functionaries of coverage to the aspect of river pollution control measures through the active involvement of the people (Action: NGOs of repute having a sound organisation infrastructure of public relations unit).
2.2.11 Awaken, educate and encourage the grassroot level functionaries belonging to such departments of state govt. as local bodies like, public health, sewerage, forestry, water supply, public works, electricity, industry, tourism etc. to take special interest in the activities which are directly related to the aspect of river pollution control. They should be particularly motivated to be more conscious of their commitment and obligation to ensure the purity of river water so that the future of the present and coming generations of the society and so also the members of their own community is safe-guarded against the health hazards. (Action: NGO having the background of specialised contribution to the area concerned).
2.3
FOR
CORE SCHEMES VIZ SEWERAGE NETWORK, SEWAGE
TREATMENT
PLANTS, PUMPS, ETC.
2.3.1 Target
Groups :
2.3.1.1 Community at large,
2.3.1.2 Business and industrial establishments.
2.3.1.3 Local municipality corporation,
2.3.1.4 Grass-root level organisation like panchayats,
2.3.1.5 Charitable trusts and religious organisation,
2.3.1.6 NGOs,
2.3.1.7 Educational, Research and Technical Institutions
2.3.1.8 Local MLAs/MPs and representatives of political parties,
2.3.1.9 Grass-root functionaries of civic bodies and concerned department of the state government,
2.3.1.10 Media agencies and individuals etc.,
2.3.2
Action Points
2.3.2.1 As nalas are the major casual factors of river pollution because of factors such as lack of adequate sewerage network, implanned growth of cities, slum settlements, non-existence of civic sense etc., there is a need to:
2.3.2.2 Estimate awareness deficits and fill them up through awareness campaigns,
2.3.2.3 Facilitate setting up of wardwise sanitation committees as ‘sanitation watch and ward societies’/action groups,
2.3.2.4 Launch a mass campaign for educating and motivating local community and families about the need to have, on site sanitation facility like community toilet complexes at the public places and household toilets at the family level,
2.3.2.5 Ensure the active participation of the business and industrial establishments of the area through their contribution to the area of liquid and waste management, including the steps to check the industrial waste effluents being allowed to mix with river water, (Action: Reputed NGO having a sound background of expertise and experience).
2.3.2.6 Facilitate promotion of urban farming and social forestry by persuading the local business and industrial establishments to undertake or sponsor these activities. These efforts should be supported by technological innovations and intervention for the fruitful adoption of the use of sewage water in urban farming and social forestry so as to have the double advantage of maximising the yield of farm and forestry produce and also to check the rivers pollution from sewage water, NRCD should sponsor pilot projects for promoting forestry on community waste land lying unused in the vicinity of river banks. The success models developed through such projects will attract private entrepreneurs to take up this activity as an income generating pre-position. (Action: Specialised NGOs, NRCD and City Corporations).
2.3.2.7 Facilitate and motivate the community to cooperate and segregate the waste at source. This being a highly specialised job has to be entrusted to a known NGO having a good track record of contribution to this area. The NGO has to share information on available technologies for recycling of waste with the local traders/manufactures associations educating and convincing them of the economic viability. For this, the success models have to be identified for fruitful replication. Such efforts need to be specially supported by NRCD through adequate funding. (Action: Known NGO, NRCD, and Industrial/business houses).
2.3.2.8 With a view to check the regular flow of industrial effluents waste in to the river generally through the nalas, there is a need to create community pressure on the pollutant units, as well as civic authorities to play their positive role. There is however, need to support those efforts by organising experience/information sharing professional meets on the available technologies of industrial effluents/waste management. While adopting this line of action, it has to be well understood that the basic principle of waste management is to add ‘value to the waste’ and this principle is applicable at all levels, be it be individual household or big industrial houses. The success model or recycling of hotel waste (Banglore) needs to be widely replicated. Similar success models working in the areas of civic sanitation and hospital waste management need to be properly identified and promoted for wider replication (Action: Eminent, expert and experienced NGO).
2.3.2.9 Core schemes have to be re-organised in order to ensure people’s participation in making the available facilities and service really meaningful. This has to be done through the provision and placement of community awareness and action at a higher order of priority. Unfortunately, so far there has not been any serious move from the side of government. Consequently, the masses in general, continue to regard these programmes as routine activities of the government with which they are hardly concerned.
2.3.2.10 It has to be well understood that even the core scheme activities, which are mostly of hardware type, need software support to involve community sincerely and systematically. The fact remains that people shall remain indifferent and apathetic towards the effective functioning of these services so long their participation in carrying on these public assets is not ensured in words and sprit.
2.3.2.11 Also, it has to be realised that there has to be a proper strategy and support system for a meaningful involvement of the community. This can only be done by highly specialised agency which has to be assigned the software aspect of awakening, educating and motivating people to consider every asset or facility created under core schemes as their own and hence to offer their voluntary support and involvement for the success of the programme. (Action: NRCD-NGO partnership to achieve the desired goal).
ANNEXURE
VIII-A
COMPLETION
REPORT
(General
Abstract of Cost)
1.
Name of the
scheme:
|
SI. No |
Sub-head/ component |
As per sanctioned Estimate |
As executed |
Variation |
Reasons for Variation |
Cost as per executed quantity & Rates as per sanctioned
Estimate |
Escalation Due to variation in
quantity Col. 12 Col. 5 |
Escalation Due to price variation Col. 8- Col.5- Col. 13 |
Remarks |
|||||
|
Item |
Qty |
Amt. |
Item |
Qty |
Amt. |
Saving (+) |
Excess (-) |
|||||||
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Certified (1) That there has been no material deviations
from the sanctioned plans and specifications other than those approved by the
competent authority.
(2) That the works have
been completed as per specifications and completion drawings enclosed
(3)
That the site has been cleared of all
malba, rubbish and surplus materials, contractors’ hutments and his materials
etc.
COMPLETION
REPORT
Component/Sub-head:
|
Sl. No |
Description of item of work |
As per sanctioned Estimate |
As executed |
Variation |
Reasons for Variation |
Cost as per executed quantity & Rates as per sanctioned
Estimate |
Escalation Due to variation in
quantities col. 14-Col. 6. |
Escalation Due to price variation Col. 10 - Col. 6 - Col. 15 |
Remarks |
|||||||
|
Qty |
Unit |
Rate |
Amt. |
Qty |
Unit |
Rate |
Amt. |
Saving (+) |
Excess (-) |
|||||||
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ministry of Environment & Forests
UTILISATION CERTIFICATE
(To be sent in duplicate to the Ministry of Environment & Forests)
for the financial year (Form____________ to _________________)
1. Title of the Project/Scheme:
2. Name of the Organisation:
3. Principal Investigator:
4. Ministry Of Environment And
Forests
letter No. and date of
sanctioning the project :
5. Amount brought forward from the previous
financial year quoting Ministry of Environment
and Forests letter no. and date on which the authority
to carry forward the said amount was given :
6. Amount received from Ministry
of Environment & Forests, during
the financial year (please give
No. and date of sanctions
Showing the amount paid)
7. Total amount that was available for
expenditure (including commitment)
incurred during the Financial Year
(S. No. 5+S. No. 6)
8. Actual Expenditure (Excluding
commitments) incurred during the financial year:
9. Unspent balance refunded if any
(Please give details of cheque
no. etc.)
10. Balance amount available at the end of the
financial year:
11. Amount allowed to be carried forward to the next financial year vide letter no. and date:
Certified that the expenditure of Rs. ______________________ (Rupees __________________ ) mentioned against column 8 was actually incurred on the Project / Scheme for the purpose for which it was sanctioned and balance amount is available on __________________ .
(Signature of (Signature of (Signature of Head
Principal Investigator) Registrar/ Accounts Officer) of the Organisation)
ACCEPTED AND COUNTERSIGNED
COMPETENT AUTHORITY
MINISTRY OF ENVIRONMENT AND FORESTS