SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












EXTENDED YAMUNA ACTION PLAN

STATE : UTTAR PARDESH

CITY : VARINDAVAN

1

Low Cost Sanitation

LCS

93.58

09/07/2001

31/03/2002

100

92.85

00.00

92.85

C

2

Additional Restoration works

I&D

132.42

06/08/2001

31/03/2002

100

124.44

00.00

124.44

C

3

Public Participation

PP

10.00

13/07/2001

31/03/2002

100

09.97

00.00

09.97

C

4

Lining works for two STPs

P-S

77.86

06/08/2001

31/03/2002

100

77.85

00.00

77.85

C

5

Improved Wood Crematoria

IWC

11.55

09/07/2001

31/03/2002

100

03.63

00.00

03.63

C












TOTAL

325.41

308.74

00.00

308.74












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS

 

SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












YAMUNA ACTION PLAN

STATE : UTTAR PARDESH

CITY : VARINDAVAN

1

Afforestation

AFF

03.90

07/07/1998

30/09/1999

100

04.87

00.00

04.87

C

2

Low Cost Sanitation

LCS

29.02

15/06/1994

100

28.90

00.00

28.90

C

3

I&D(Part-I)

I&D

34.33

15/02/1995

31/07/1997

100

74.51

00.00

74.51

C

4

I&D Gyan Gundri Area

I&D

210.77

16/02/1996

30/11/1998

100

247.09

00.00

247.09

C

5

I&D and STP (Part-IV)Kalideh

I&D

98.33

06/05/1998

31/03/1999

100

106.32

00.00

106.32

C

6

Land Acquisition

LA

04.05

15/06/1994

100

16.33

00.00

16.33

C

7

Public Participation

PP

10.26

06/08/1998

100

09.71

00.00

09.71

C

8

Sewage Treatment Plant (4 MLD, OP)

STP

21.90

15/06/1994

31/08/1997

100

51.09

00.00

51.09

C

9

Improved Wood Crematoria

IWC

02.96

14/06/1994

31/03/1995

100

04.81

00.00

04.81

C












TOTAL

415.52

543.63

00.00

543.63












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS