SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE :  MAHARASHTRA

CITY :  TRIMBAKESHWAR

1

Afforestation

AFF

11.70

08/01/2002

31/03/2003

100

11.70

00.00

11.70

C

2

Low Cost Sanitation

LCS

138.35

08/01/2002

31/03/2003

100

143.44

00.00

143.44

C

3

Interception & Diversion

I&D

337.10

08/01/2002

31/03/2003

100

304.62

00.00

304.62

C

4

Land Acquisition

LA

22.00

08/01/2002

31/03/2003

100

00.00

00.00

00.00

C

5

Public Participation

PP

10.80

08/01/2002

31/03/2003

100

05.63

00.00

05.63

C

6

Development of ponds

OTH

134.79

08/01/2002

31/03/2003

100

134.77

00.00

134.77

C

7

Kushawarta Tirth Development

OTH

151.25

08/01/2002

31/03/2003

100

217.94

00.00

217.94

C

8

River Front Development

RFD

318.60

08/01/2002

31/03/2003

100

251.47

00.00

251.47

C

9

Sewage Treatment Plant

STP

32.40

08/01/2002

31/03/2003

100

70.39

00.00

70.39

C

10

Solid Waste Management

SWM

07.02

08/01/2002

31/03/2003

100

08.72

00.00

08.72

C












TOTAL

1164.01

1148.68

00.00

1148.68












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS