SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE :  TAMILNADU

CITY :  TRICHY

1

Afforestation

AFF

05.40

10/07/2003

30/09/2003

100

05.12

00.00

05.12

C

2

Low Cost Sanitation

LCS

36.13

13/02/1996

30/06/1997

100

40.11

00.00

40.11

C

3

I&D (Part-I)

I&D

92.50

04/12/1996

31/12/1998

100

142.14

00.00

142.14

C

4

I&D (Part-II)

I&D

46.64

04/12/1996

31/12/1998

100

54.38

00.00

54.38

C

5

I&D(Part-III)

I&D

71.87

27/11/1996

31/12/1998

100

58.27

00.00

58.27

C

6

River Front Development

RFD

16.80

14/02/1996

30/09/1996

100

16.06

00.00

16.06

C

7

Sewage Treatment Plant

STP

109.73

23/12/1999

31/12/2000

100

107.00

00.00

107.00

C

8

Improved Wood Crematoria

IWC

09.74

15/02/1996

30/09/1996

0

00.00

00.00

00.00

O












TOTAL

388.81

423.08

00.00

423.08












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS