SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












GANGA ACTION PLAN - II(MAIN STEM)

STATE :  WEST BENGAL

CITY :  TOLLY'S NALLAH

1

Afforestation

AFF

03.35

26/08/2004

31/12/2005

100

00.00

00.00

00.00

C

2

Interception & Diversion

I&D

332.47

17/10/2000

31/12/2001

70

434.19

00.00

434.19

O

3

Interception & Diversion

I&D

1788.49

27/11/1998

31/12/2000

100

1162.33

00.00

1162.33

C

4

Lifting Station for Pollution Abatement

I&D

263.80

20/08/2009

31/08/2010

0

00.00

00.00

00.00

O

5

Public Participation & Awareness Programme

PP

11.34

25/08/2004

31/12/2005

100

06.75

00.00

06.75

C












TOTAL

2399.45

1603.27

00.00

1603.27












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS