SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE : PUNJAB

CITY : TANDA

1

Sewerage and Sewage Treatment Plant (4 mld)

STP

2288.62

06/10/2010

30/09/2012

0

00.00

00.00

00.00

O












TOTAL

2288.62

00.00

00.00

00.00












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS