SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












GOMATI ACTION PLAN

STATE :  UTTAR PARDESH

CITY :  SULTANPUR

1

Low Cost Sanitation

LCS

16.35

09/08/1994

31/08/1995

100

12.58

00.00

12.58

C

2

I&D (Part-I)

I&D

39.65

11/10/1995

31/12/1996

100

54.65

00.00

54.65

C

3

I&D (Part-II)

I&D

218.96

01/08/1996

30/09/1998

100

237.60

00.00

237.60

C

4

Land Acquisition

LA

40.92

15/06/1995

31/12/1995

100

04.50

00.00

04.50

C

5

Sewage Treatment Plant

STP

117.34

29/11/1996

31/12/1998

100

141.48

00.00

141.48

C

6

Improved Wood Crematoria

IWC

01.44

08/03/1995

31/12/1995

100

01.63

00.00

01.63

C












TOTAL

434.66

452.44

00.00

452.44












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS