SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












EXTENDED YAMUNA ACTION PLAN

STATE : UTTAR PARDESH

CITY : SAHARANPUR

1

Remedial Measures for LCS

LCS

01.12

05/07/2001

28/02/2002

100

01.06

00.00

01.06

C

2

Low Cost Sanitation

LCS

64.80

07/09/2001

31/03/2002

100

51.69

00.00

51.69

C

3

Constrution of Addl. Slump for the MPS

I&D

56.36

27/06/2001

31/03/2002

100

54.74

00.00

54.74

C

4

DG set at IPS Govindpur

I&D

12.70

06/08/2001

31/12/2001

100

10.49

00.00

10.49

C

5

Public Participation

PP

12.50

31/12/2002

100

12.50

00.00

12.50

C

6

Fire Fighting System (38 mld)

P-S

26.91

26/06/2001

28/02/2002

100

26.31

00.00

26.31

C

7

Fire Fighting System (I&D Rehabilitation Part-I)

P-S

104.73

27/06/2001

31/03/2002

100

111.25

00.00

111.25

C












TOTAL

279.12

268.04

00.00

268.04












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS

 

SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












YAMUNA ACTION PLAN

STATE : UTTAR PARDESH

CITY : SAHARANPUR

1

Low Cost Sanitation

LCS

29.89

13/01/1995

31/03/1997

100

28.04

00.00

28.04

C

2

I&D C&G Part-I

I&D

220.24

28/10/1996

31/10/1998

100

245.13

00.00

245.13

C

3

I&D C&G Part-II

I&D

258.27

28/10/1996

31/10/1998

100

250.18

00.00

250.18

C

4

I&D(Part-III)

I&D

167.34

29/11/1996

31/12/1998

100

181.09

00.00

181.09

C

5

I&D (Part-II)

I&D

182.32

24/10/1997

31/03/1999

100

174.06

00.00

174.06

C

6

I&D Part-III(Suplementary DPR)

I&D

29.07

13/09/1999

21/12/1998

100

15.74

00.00

15.74

C

7

Land Acquisition

LA

23.40

16/01/1995

30/06/1997

100

190.41

00.00

190.41

C

8

Public Participation

PP

10.80

11/11/1999

29/02/2000

100

10.96

00.00

10.96

C

9

Sewage Treatment Plant(38 mld, UASB)

STP

945.78

29/07/1998

31/12/1999

100

1035.19

00.00

1035.19

C

10

Improved Wood Crematoria

IWC

02.17

01/02/1995

31/03/1996

100

02.79

00.00

02.79

C












TOTAL

1869.28

2133.59

00.00

2133.59












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS