SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












GAP II

STATE :  UTTRAKHAND

CITY :  RANIPUR

1

Low Cost Sanitation

LCS

38.76

27/04/1998

31/03/1999

100

36.48

00.00

36.48

C

2

Renovation of Existing Out Fall Gravity Sewer

I&D

02.39

27/04/1998

31/10/1998

100

02.26

00.00

02.26

C

3

Interception and Diversion in Zone-E-I

I&D

122.45

17/08/2001

17/08/2003

100

109.09

00.00

109.09

C

4

Reorganisation of Seweage System of Zone-2(Jwalpur

I&D

197.67

24/06/2003

30/11/2005

50

238.71

00.00

238.71

O

5

Sewage Treatment Plant at Sarai Jamalpur

STP

31.28

17/08/2001

17/08/2003

50

26.82

00.00

26.82

O












TOTAL

392.55

413.36

00.00

413.36












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS