SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












YAMUNA ACTION PLAN

STATE :  HARYANA

CITY :  RADAUR

1

Interception & Diversion

I&D

59.00

23/10/1997

30/11/1998

100

48.84

00.00

48.84

C

2

Sewage Treatment Plant and Main Pumping Station

STP

49.86

18/10/2000

30/09/2001

100

42.27

00.00

42.27

C












TOTAL

108.86

91.11

00.00

91.11












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS