SANCTION/PROGRESS OF
SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
GANGA ACTION PLAN - II(MAIN STEM) |
||||||||||
|
STATE : BIHAR |
||||||||||
|
CITY : PATNA |
||||||||||
|
1 |
River Front Development |
RFD |
79.85 |
29/03/1996 |
30/09/1996 |
100 |
65.48 |
00.00 |
65.48 |
C |
|
2 |
River Front Development |
RFD |
30.13 |
27/03/2002 |
31/12/2002 |
99 |
28.61 |
00.00 |
28.61 |
O |
|
3 |
River Front Development |
RFD |
19.44 |
27/03/2002 |
31/12/2002 |
98 |
14.83 |
00.00 |
14.83 |
O |
|
4 |
Diesal Crematoria |
IWC |
53.20 |
27/03/2002 |
30/09/2003 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
182.62 |
108.93 |
00.00 |
108.93 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C --> COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE
PUMPING STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |