SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












GAP II

STATE :  WEST BENGAL

CITY :  NAIHATI

1

Afforestation

AFF

05.22

20/08/2004

31/12/2005

100

05.20

00.00

05.20

C

2

Electric Crematoria

CRE

161.32

13/07/2009

31/12/2009

70

12.48

00.00

12.48

O

3

Interception & Diversion

I&D

63.73

31/10/1997

31/12/1998

100

59.49

00.00

59.49

C

4

Lifting Station

I&D

57.25

10/06/2002

31/03/2004

100

72.40

00.00

72.40

C

5

Interception & Diversion

I&D

195.00

31/03/2008

31/03/2009

100

25.66

00.00

25.66

C

6

Public Participation & Awareness Programme

PP

09.73

03/06/2004

31/12/2005

100

09.70

00.00

09.70

C

7

Main Pumping Station-I

MPS

164.62

22/03/2004

31/12/2005

100

83.04

00.00

83.04

C

8

Main Pumping Station-2

MPS

148.13

31/03/2004

31/12/2005

100

69.08

00.00

69.08

C

9

Main Pumping Satation-3

MPS

234.77

31/03/2004

31/12/2005

100

230.42

00.00

230.42

C

10

River Front Development

RFD

09.60

18/03/2002

31/03/2003

100

09.60

00.00

09.60

C

11

River Front Development-II

RFD

160.97

29/04/2008

31/10/2008

100

160.55

00.00

160.55

C

12

Sewage Treatment Plant(a)

STP

250.35

26/04/2006

31/12/2006

100

250.00

00.00

250.00

C

13

Sewage Treatment Plant(b)

STP

161.05

24/04/2006

31/12/2006

100

160.45

00.00

160.45

C

14

Sewage Treatment Plant

STP

264.32

24/01/2005

31/03/2006

100

205.00

00.00

205.00

C












TOTAL

1886.06

1353.07

00.00

1353.07












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS