SANCTION/PROGRESS OF
SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
NATIONAL RIVER CONSERVATION PLAN |
||||||||||
|
STATE : MADHYA PRADESH |
||||||||||
|
CITY : NAGDA |
||||||||||
|
1 |
Low Cost Sanitation |
LCS |
12.53 |
11/01/1999 |
31/12/1999 |
100 |
12.53 |
00.00 |
12.53 |
C |
|
2 |
Interception & Diversion |
I&D |
229.44 |
17/11/1997 |
30/11/1999 |
100 |
224.62 |
00.00 |
224.62 |
C |
|
3 |
Sewage Treatment Plant |
STP |
37.29 |
10/11/1998 |
30/11/1999 |
100 |
41.28 |
00.00 |
41.28 |
C |
|
4 |
Improved Wood Crematoria |
IWC |
02.85 |
07/07/1997 |
31/03/1998 |
100 |
02.50 |
00.00 |
02.50 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
282.11 |
280.92 |
00.00 |
280.92 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C --> COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE
PUMPING STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |