SANCTION/PROGRESS OF
SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
NATIONAL RIVER CONSERVATION PLAN |
||||||||||
|
STATE : TAMILNADU |
||||||||||
|
CITY : MYLADUTHURAI |
||||||||||
|
1 |
Intercepton & Diversion + Sewage
Treatment Plant |
I&D |
3963.17 |
26/12/2001 |
30/06/2004 |
100 |
4069.81 |
00.00 |
4069.81 |
C |
|
2 |
Solid Waste Management ( 7 addl. town) |
OTH |
159.00 |
10/12/2007 |
31/03/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
3 |
River Front Development(7 Additional towns) |
RFD |
51.27 |
07/06/2004 |
28/02/2005 |
100 |
21.70 |
00.00 |
21.70 |
C |
|
4 |
Wood Based Crematoria (7 Additional town) |
IWC |
09.12 |
07/06/2004 |
28/02/2005 |
0 |
02.17 |
00.00 |
02.17 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
4182.56 |
4093.68 |
00.00 |
4093.68 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C --> COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE
PUMPING STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |