SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












EXTENDED YAMUNA ACTION PLAN

STATE : UTTAR PARDESH

CITY : MUZAFFARNAGAR

1

Low cost Sanitation

LCS

33.59

06/07/2001

28/02/2002

100

17.96

00.00

17.96

C

2

I&D (Part-III)

I&D

52.87

06/07/2001

30/09/2001

100

50.48

00.00

50.48

C

3

Public Participation

PP

10.00

31/03/2002

100

09.82

00.00

09.82

C

4

Miscellanous at STP

P-S

10.06

07/09/2001

31/12/2001

100

09.78

00.00

09.78

C












TOTAL

106.52

88.04

00.00

88.04












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS

 

SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












YAMUNA ACTION PLAN

STATE : UTTAR PARDESH

CITY : MUZAFFARNAGAR

1

Low Cost Sanitation

LCS

34.26

09/06/1994

31/12/1997

100

42.50

00.00

42.50

C

2

I&D(Part-I) Western Zone

I&D

297.04

31/10/1995

31/12/1998

100

301.85

00.00

301.85

C

3

I&D-II(Western Zone)

I&D

247.64

06/12/1996

31/12/1998

100

258.05

00.00

258.05

C

4

Land Acquisition

LA

149.19

05/09/1994

31/12/1997

100

357.51

00.00

357.51

C

5

Public Participation

PP

10.80

02/09/1999

31/01/2000

100

10.42

00.00

10.42

C

6

Sewage Treatment Plant

STP

109.37

27/12/1996

31/12/1998

100

198.57

00.00

198.57

C

7

Improved Wood Crematoria

IWC

02.11

09/08/1994

31/03/1996

100

02.08

00.00

02.08

C












TOTAL

850.41

1170.98

00.00

1170.98












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS