SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE :  ANDRA PRADESH

CITY :  MANCHARIAL

1

Low Cost Sanitation

LCS

22.20

27/12/1995

30/06/1997

100

19.06

00.00

19.06

C

2

Interception and Diversion

I&D

132.66

27/10/1997

30/09/1999

100

124.91

00.00

124.91

C

3

River Front Development

RFD

17.50

23/11/1995

100

17.19

00.00

17.19

C

4

Sewage Treatment Plant

STP

26.65

14/11/2000

31/12/2001

100

28.72

00.00

28.72

C

5

Sewage Treatment Plant

STP

34.18

14/11/2000

31/12/2001

100

34.18

00.00

34.18

C












TOTAL

233.19

224.06

00.00

224.06












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS