SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE :  TAMILNADU

CITY :  MADURAI

1

Interception & Diversion(Part-I)

I&D

4253.00

07/01/2002

31/12/2003

100

4665.10

00.00

4665.10

C

2

Interception & Diversion(Part-II)

I&D

7024.85

09/07/2002

31/12/2004

100

6519.24

00.00

6519.24

C

3

Interception & Diversion Phase-IV

I&D

731.55

20/07/2006

31/07/2008

0

00.00

00.00

00.00

O

4

Sewage Treatment Plant Phase-II

STP

1014.78

24/07/2006

30/04/2007

0

00.00

00.00

00.00

D












TOTAL

13024.18

11184.34

00.00

11184.34












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS