SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE : PUNJAB

CITY : LUDHIANA

1

Afforestation/Plantation

AFF

06.50

29/06/1998

30/09/1999

100

02.69

00.00

02.69

C

2

Low Cost Sanitation

LCS

186.72

05/06/1997

31/12/1998

100

93.98

00.00

93.98

C

3

I&D (Part-I)

I&D

128.97

23/02/1996

30/09/1997

100

106.60

00.00

106.60

C

4

I&D (Part-II)

I&D

287.54

15/03/1996

31/03/1998

100

269.82

00.00

269.82

C

5

I&D (Part-III)

I&D

250.42

05/05/1997

31/12/1998

100

192.20

00.00

192.20

C

6

I&D (Part-IV)

I&D

567.85

03/08/1998

30/06/2000

100

474.18

00.00

474.18

C

7

I&D (Part-V)

I&D

177.30

05/05/1997

31/12/1998

100

126.53

00.00

126.53

C

8

I&D (Part-VI)

I&D

222.23

05/05/1997

31/03/1999

100

213.87

00.00

213.87

C

9

I&D (Part-VII)

I&D

184.05

04/08/1997

31/03/1999

100

159.50

00.00

159.50

C

10

Tapping of open surface drains

I&D

40.90

07/09/2005

31/08/2006

0

00.00

00.00

00.00

O

11

LA (Bhattian STP)

LA

112.19

08/11/1995

100

1723.06

00.00

1723.06

C

12

LA (Baloke STP)

LA

139.50

06/11/1995

100

2129.00

00.00

2129.00

C

13

Land Acquisition(Jamalpur STP)

LA

48.43

28/01/1997

100

942.37

00.00

942.37

C

14

Public Participation & Awareness Programme

PP

10.80

13/10/2004

31/12/2006

100

05.24

00.00

05.24

C

15

Main Pumping Station

MPS

802.55

06/08/2001

31/08/2003

100

749.85

-00.05

749.80

C

16

Main Pumping Station Baloke

MPS

1491.72

16/08/2001

31/08/2003

100

1527.44

00.00

1527.44

C

17

Main Pumping Station at Jamalpur

MPS

384.33

06/08/2001

31/08/2003

100

323.18

00.00

323.18

C

18

STP at Bhattian

STP

3484.58

02/07/2002

31/12/2004

100

3727.99

10.00

3737.99

C

19

STP at Jamalpur

STP

1345.99

30/06/2003

30/09/2005

92

1430.66

00.00

1430.66

O

20

STP Baloke

STP

3478.64

02/07/2002

31/12/2004

100

4237.20

00.00

4237.20

C












TOTAL

13351.21

18435.35

09.95

18445.30












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS