|
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
NATIONAL RIVER CONSERVATION PLAN |
||||||||||
|
STATE : PUNJAB |
||||||||||
|
CITY : LUDHIANA |
||||||||||
|
1 |
Afforestation/Plantation |
AFF |
06.50 |
29/06/1998 |
30/09/1999 |
100 |
02.69 |
00.00 |
02.69 |
C |
|
2 |
Low Cost Sanitation |
LCS |
186.72 |
05/06/1997 |
31/12/1998 |
100 |
93.98 |
00.00 |
93.98 |
C |
|
3 |
I&D (Part-I) |
I&D |
128.97 |
23/02/1996 |
30/09/1997 |
100 |
106.60 |
00.00 |
106.60 |
C |
|
4 |
I&D (Part-II) |
I&D |
287.54 |
15/03/1996 |
31/03/1998 |
100 |
269.82 |
00.00 |
269.82 |
C |
|
5 |
I&D (Part-III) |
I&D |
250.42 |
05/05/1997 |
31/12/1998 |
100 |
192.20 |
00.00 |
192.20 |
C |
|
6 |
I&D (Part-IV) |
I&D |
567.85 |
03/08/1998 |
30/06/2000 |
100 |
474.18 |
00.00 |
474.18 |
C |
|
7 |
I&D (Part-V) |
I&D |
177.30 |
05/05/1997 |
31/12/1998 |
100 |
126.53 |
00.00 |
126.53 |
C |
|
8 |
I&D (Part-VI) |
I&D |
222.23 |
05/05/1997 |
31/03/1999 |
100 |
213.87 |
00.00 |
213.87 |
C |
|
9 |
I&D (Part-VII) |
I&D |
184.05 |
04/08/1997 |
31/03/1999 |
100 |
159.50 |
00.00 |
159.50 |
C |
|
10 |
Tapping of open surface drains |
I&D |
40.90 |
07/09/2005 |
31/08/2006 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
11 |
LA (Bhattian STP) |
LA |
112.19 |
08/11/1995 |
100 |
1723.06 |
00.00 |
1723.06 |
C |
|
|
12 |
LA (Baloke STP) |
LA |
139.50 |
06/11/1995 |
100 |
2129.00 |
00.00 |
2129.00 |
C |
|
|
13 |
Land Acquisition(Jamalpur
STP) |
LA |
48.43 |
28/01/1997 |
100 |
942.37 |
00.00 |
942.37 |
C |
|
|
14 |
Public Participation & Awareness Programme |
PP |
10.80 |
13/10/2004 |
31/12/2006 |
100 |
05.24 |
00.00 |
05.24 |
C |
|
15 |
Main Pumping Station |
MPS |
802.55 |
06/08/2001 |
31/08/2003 |
100 |
749.85 |
-00.05 |
749.80 |
C |
|
16 |
Main Pumping Station Baloke |
MPS |
1491.72 |
16/08/2001 |
31/08/2003 |
100 |
1527.44 |
00.00 |
1527.44 |
C |
|
17 |
Main Pumping Station at Jamalpur |
MPS |
384.33 |
06/08/2001 |
31/08/2003 |
100 |
323.18 |
00.00 |
323.18 |
C |
|
18 |
STP at Bhattian |
STP |
3484.58 |
02/07/2002 |
31/12/2004 |
100 |
3727.99 |
10.00 |
3737.99 |
C |
|
19 |
STP at Jamalpur |
STP |
1345.99 |
30/06/2003 |
30/09/2005 |
92 |
1430.66 |
00.00 |
1430.66 |
O |
|
20 |
STP Baloke |
STP |
3478.64 |
02/07/2002 |
31/12/2004 |
100 |
4237.20 |
00.00 |
4237.20 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
13351.21 |
18435.35 |
09.95 |
18445.30 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |