SANCTION/PROGRESS OF
SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
NATIONAL RIVER CONSERVATION PLAN |
||||||||||
|
STATE : TAMILNADU |
||||||||||
|
CITY : KUMBAKONAM |
||||||||||
|
1 |
Low Cost Sanitation |
LCS |
73.71 |
16/09/2003 |
30/09/2004 |
0 |
36.39 |
00.00 |
36.39 |
O |
|
2 |
Interception & Diversion (Phase-I) |
I&D |
264.08 |
20/12/2001 |
30/09/2002 |
100 |
263.90 |
00.22 |
264.12 |
C |
|
3 |
Interception & Diversion |
I&D |
2902.11 |
26/12/2001 |
31/12/2003 |
100 |
3960.92 |
00.21 |
3961.13 |
C |
|
4 |
River Front Development |
RFD |
14.87 |
16/09/2003 |
30/09/2004 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
5 |
Bathing Ghat(10 Nos.) |
RFD |
27.30 |
16/09/2003 |
30/09/2004 |
0 |
05.96 |
00.00 |
05.96 |
O |
|
6 |
Dhobikhana (1 Nos) |
RFD |
12.96 |
16/09/2003 |
30/09/2004 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
7 |
Sewage Treatment Plant (17 mld) |
STP |
664.04 |
10/07/2008 |
31/12/2009 |
80 |
584.26 |
00.00 |
584.26 |
O |
|
8 |
Solid Waste Management |
SWM |
164.16 |
16/09/2003 |
30/09/2004 |
0 |
127.20 |
00.00 |
127.20 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
4123.23 |
4978.63 |
00.43 |
4979.06 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C --> COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE
PUMPING STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |