SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE : KARNATKA

CITY : KRNAGAR

1

Low Cost Sanitation

LCS

03.50

18/03/1996

30/07/1997

100

05.51

00.00

05.51

C

2

I&D (Part-I)

I&D

11.35

05/12/1996

30/06/1998

100

36.71

00.00

36.71

C

3

River Front Development

RFD

02.14

28/04/1997

30/11/1997

0

00.00

00.00

00.00

O

4

Sewage Treatment Plant(WSP)

STP

24.61

09/08/2000

100

27.92

00.00

27.92

C

5

Crematoria(IWB)

IWC

00.91

18/03/1996

30/07/1997

100

02.39

00.00

02.39

C












TOTAL

42.51

72.53

00.00

72.53












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS

Top of Form

Bottom of Form