SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE : KARNATKA

CITY : KOLLEGAL

1

Low Cost Sanitation

LCS

17.60

17/03/1996

30/09/1997

90

16.33

00.00

16.33

O

2

Interception & Diversion

I&D

47.43

17/07/2003

31/07/2004

100

44.75

00.00

44.75

C

3

River Front Development

RFD

05.40

07/07/2003

31/01/2004

0

00.00

00.00

00.00

O

4

Sewage Treatment Plan

STP

39.24

09/11/2000

30/11/2001

100

46.56

00.00

46.56

C












TOTAL

109.67

107.64

00.00

107.64












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS