SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












YAMUNA ACTION PLAN

STATE : HARYANA

CITY : KARNAL

1

Afforestation

AFF

02.25

12/08/1998

31/03/1999

100

02.17

00.00

02.17

C

2

Boundry Wall STP-II

BW

16.86

07/07/1995

30/04/1997

100

16.85

00.00

16.85

C

3

Low Cost Sanitation

LCS

42.83

11/12/1995

31/05/1997

100

37.45

00.00

37.45

C

4

I&D works Zone-I&II

I&D

203.62

19/09/1994

30/04/1997

100

243.29

00.00

243.29

C

5

Land Acquisition for STP

LA

207.00

13/12/1996

30/06/1997

100

209.12

00.00

209.12

C

6

Public Participation

PP

10.80

08/12/1999

29/02/2000

100

00.01

00.00

00.01

C

7

MPS Zone I

MPS

287.31

24/12/1996

30/04/1997

100

275.64

00.00

275.64

C

8

STP-I (40 mld)

STP

1271.94

13/12/1996

30/04/1997

100

1232.28

00.00

1232.28

C

9

STP-II(8 mld)

STP

115.60

12/06/1996

30/04/1997

100

285.35

00.00

285.35

C

10

Improved Wood Crematoria

IWC

04.46

10/08/1994

30/04/1997

100

04.46

00.00

04.46

C












TOTAL

2162.67

2306.62

00.00

2306.62












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS