SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
NATIONAL RIVER CONSERVATION PLAN |
||||||||||
|
STATE : PUNJAB |
||||||||||
|
CITY : KAPURTHALA |
||||||||||
|
1 |
Afforestation |
AFF |
03.78 |
04/07/2001 |
30/06/2003 |
100 |
00.44 |
00.00 |
00.44 |
C |
|
2 |
Interception & Diversion |
I&D |
340.20 |
04/07/2001 |
30/06/2003 |
100 |
275.87 |
00.00 |
275.87 |
C |
|
3 |
Land Acquisition |
LA |
247.00 |
04/07/2001 |
30/06/2003 |
100 |
202.33 |
00.00 |
202.33 |
C |
|
4 |
Public Participation |
PP |
02.70 |
04/07/2001 |
30/06/2003 |
100 |
03.32 |
00.00 |
03.32 |
C |
|
5 |
STP(Including effluent channel) |
STP |
662.58 |
04/07/2001 |
30/06/2003 |
100 |
796.79 |
00.00 |
796.79 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
1256.26 |
1278.75 |
00.00 |
1278.75 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |