SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
EXTENDED YAMUNA ACTION PLAN |
||||||||||
|
STATE : UTTAR PARDESH |
||||||||||
|
CITY : GHAZIABAD |
||||||||||
|
1 |
Low Cost Sanitation |
LCS |
252.29 |
27/06/2001 |
31/03/2002 |
100 |
211.10 |
00.00 |
211.10 |
C |
|
2 |
I&D Zone-IV (CHA Part-I) |
I&D |
139.32 |
04/07/2001 |
31/03/2002 |
100 |
124.87 |
00.00 |
124.87 |
C |
|
3 |
Interception and Diversion |
I&D |
269.32 |
29/10/2002 |
31/12/2002 |
100 |
251.14 |
00.00 |
251.14 |
C |
|
4 |
Public Participation |
PP |
11.40 |
13/07/2001 |
31/03/2002 |
100 |
11.38 |
00.00 |
11.38 |
C |
|
5 |
Networking (15 towns) |
OTH |
38.25 |
27/07/2001 |
31/01/2002 |
100 |
38.25 |
00.00 |
38.25 |
C |
|
6 |
Intelligent Project Management |
OTH |
10.37 |
27/02/2003 |
29/02/2004 |
100 |
00.00 |
00.00 |
00.00 |
C |
|
7 |
Fire Fighting System (70 mld) |
P-S |
31.67 |
27/06/2001 |
31/03/2002 |
100 |
31.67 |
00.00 |
31.67 |
C |
|
8 |
fire Protection Works (56 mld,
THA Area) |
P-S |
37.18 |
28/06/2001 |
28/02/2002 |
100 |
34.80 |
00.00 |
34.80 |
C |
|
9 |
Laboratory Equip. at Ghaziabad,Saharanpur
& Noida |
P-S |
07.50 |
06/07/2001 |
31/12/2001 |
100 |
07.40 |
00.00 |
07.40 |
C |
|
10 |
Miscellaneous |
P-S |
43.02 |
07/09/2001 |
31/03/2002 |
100 |
43.01 |
00.00 |
43.01 |
C |
|
11 |
Miscellaneous |
P-S |
20.48 |
10/09/2001 |
31/03/2002 |
100 |
20.48 |
00.00 |
20.48 |
C |
|
12 |
Remedial Measures for Non-Seweage
Facilities |
PLC |
00.64 |
06/07/2001 |
31/12/2001 |
100 |
00.55 |
00.00 |
00.55 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
861.44 |
774.65 |
00.00 |
774.65 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |
|
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN-II |
||||||||||
|
STATE : UTTAR PARDESH |
||||||||||
|
CITY : GHAZIABAD |
||||||||||
|
1 |
Reform Action Plan for 8 towns |
OTH |
170.03 |
24/11/2006 |
100 |
169.08 |
-00.02 |
169.06 |
C |
|
|
2 |
Consultancy Services for Master Plan |
OTH |
1193.58 |
29/11/2006 |
30/04/2009 |
100 |
1092.46 |
42.48 |
1134.94 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
1363.61 |
1261.54 |
42.46 |
1304.00 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |
|
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN |
||||||||||
|
STATE : UTTAR PARDESH |
||||||||||
|
CITY : GHAZIABAD |
||||||||||
|
1 |
Afforestation |
AFF |
02.19 |
08/12/1998 |
30/09/1999 |
100 |
02.19 |
00.00 |
02.19 |
C |
|
2 |
Low Cost Sanitation |
LCS |
34.13 |
09/06/1994 |
30/11/1995 |
100 |
40.68 |
00.00 |
40.68 |
C |
|
3 |
I&D (Part-I) in Trans-Hindon |
I&D |
149.20 |
22/12/1994 |
30/06/1996 |
100 |
146.08 |
00.00 |
146.08 |
C |
|
4 |
I&D(Part-II) in Trans-Hindon |
I&D |
273.92 |
22/12/1994 |
30/06/1996 |
100 |
266.87 |
00.00 |
266.87 |
C |
|
5 |
I&D(Part-III) in Trans-Hindon |
I&D |
471.68 |
16/03/1995 |
31/01/1998 |
100 |
468.41 |
00.00 |
468.41 |
C |
|
6 |
I&D(Part-IV) in Trans-Hindon |
I&D |
534.72 |
16/03/1995 |
15/01/1998 |
100 |
519.93 |
00.00 |
519.93 |
C |
|
7 |
I&D(Part-I) Cis-Hindon |
I&D |
204.53 |
16/02/1995 |
15/10/1997 |
100 |
357.38 |
00.00 |
357.38 |
C |
|
8 |
I&D(Part-II) Cis-Hindon |
I&D |
892.21 |
12/07/1995 |
31/05/1998 |
100 |
872.65 |
00.00 |
872.65 |
C |
|
9 |
Land Acquisition |
LA |
600.28 |
19/01/1995 |
31/12/1996 |
100 |
1160.71 |
00.00 |
1160.71 |
C |
|
10 |
Main Pumping Station THA & Rising Main |
MPS |
875.06 |
04/11/1997 |
31/03/1999 |
100 |
735.45 |
00.00 |
735.45 |
C |
|
11 |
Main Pumping Station |
MPS |
750.17 |
29/07/1998 |
30/09/1999 |
100 |
666.24 |
00.00 |
666.24 |
C |
|
12 |
STP(Cis-Hindon Area,70 mld) |
STP |
112.73 |
14/02/1997 |
31/12/1997 |
100 |
1764.56 |
00.00 |
1764.56 |
C |
|
13 |
STP(Trans Hindon Area,56 mld) |
STP |
1368.89 |
29/08/1997 |
31/08/1999 |
100 |
1506.59 |
00.00 |
1506.59 |
C |
|
14 |
Improved Wood Crematoria |
IWC |
13.83 |
09/06/1994 |
30/06/1995 |
100 |
13.10 |
00.00 |
13.10 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
6283.54 |
8520.84 |
00.00 |
8520.84 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |