SANCTION/PROGRESS OF SCHEMES UNDER
NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
NATIONAL RIVER CONSERVATION PLAN |
||||||||||
|
STATE : SIKKIM |
||||||||||
|
CITY : GANGTOK |
||||||||||
|
1 |
Sewerage and Sewage Treatment Plant |
STP |
1581.38 |
28/03/2005 |
31/03/2008 |
96 |
1611.00 |
100.79 |
1711.79 |
O |
|
2 |
STP and Rehabilitation of Sewer Main (Bye Pass) |
STP |
799.20 |
11/08/2009 |
31/08/2010 |
40 |
144.00 |
471.00 |
615.00 |
O |
|
3 |
Pollution abatement works Zone-IV |
STP |
7692.00 |
04/03/2010 |
31/03/2013 |
5 |
435.65 |
3000.35 |
3436.00 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
10072.58 |
2190.65 |
3572.14 |
5762.79 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C --> COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE
PUMPING STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |