SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
EXTENDED YAMUNA ACTION PLAN |
||||||||||
|
STATE : HARYANA |
||||||||||
|
CITY : FARIDABAD |
||||||||||
|
1 |
Low Cost Sanitation(23 Nos.) |
LCS |
274.81 |
05/07/2001 |
28/02/2001 |
100 |
271.32 |
00.00 |
271.32 |
C |
|
2 |
Interception & Diversion |
I&D |
276.17 |
22/01/2001 |
100 |
273.45 |
00.00 |
273.45 |
C |
|
|
3 |
Public Participation ( all 6 towns) |
PP |
77.00 |
16/07/2001 |
31/03/2002 |
100 |
75.59 |
00.00 |
75.59 |
C |
|
4 |
Additional Sludge Drying Beds (20 mld) |
P-S |
54.62 |
03/07/2001 |
31/12/2001 |
100 |
50.95 |
00.00 |
50.95 |
C |
|
5 |
Laboratory Equipment (all 6 towns) |
P-S |
09.00 |
03/07/2001 |
31/10/2001 |
100 |
08.72 |
00.00 |
08.72 |
C |
|
6 |
Pilot Plant at 20 mld STP
Zone-I |
P-S |
103.95 |
10/09/2001 |
31/03/2002 |
100 |
104.04 |
00.00 |
104.04 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
795.55 |
784.07 |
00.00 |
784.07 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |
|
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN-II |
||||||||||
|
STATE : HARYANA |
||||||||||
|
CITY : FARIDABAD |
||||||||||
|
1 |
Additional Sewerage Works |
I&D |
83.90 |
12/03/2007 |
30/09/2007 |
100 |
65.10 |
00.00 |
65.10 |
C |
|
2 |
Sewer lines (Phase-II/Stage-II) |
I&D |
833.36 |
07/11/2007 |
30/04/2007 |
100 |
929.17 |
00.00 |
929.17 |
C |
|
3 |
Public Participation & Awareness for 6 towns |
PP |
410.44 |
29/03/2007 |
31/05/2007 |
100 |
345.12 |
10.85 |
355.97 |
C |
|
4 |
Public Participation and Awareness |
PP |
71.66 |
28/03/2008 |
31/03/2010 |
100 |
33.79 |
06.15 |
39.94 |
C |
|
5 |
Consultancy for Preparation of Reform Action Plan |
OTH |
149.43 |
19/09/2006 |
100 |
149.07 |
00.00 |
149.07 |
C |
|
|
6 |
Consultancy for Engineering Technology |
OTH |
202.39 |
19/09/2006 |
100 |
202.95 |
00.00 |
202.95 |
C |
|
|
7 |
DPR Preparation for Sewerage works in eight towns |
OTH |
1081.87 |
21/11/2006 |
31/01/2010 |
96 |
945.93 |
46.66 |
992.59 |
O |
|
8 |
Common ReformsImplementation
programmes |
OTH |
1182.00 |
07/07/2009 |
31/12/2009 |
90 |
719.45 |
126.84 |
846.29 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
4015.05 |
3390.58 |
190.50 |
3581.08 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |
|
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN |
||||||||||
|
STATE : HARYANA |
||||||||||
|
CITY : FARIDABAD |
||||||||||
|
1 |
Low Cost Sanitation |
LCS |
68.38 |
13/09/1995 |
31/05/1997 |
100 |
75.37 |
00.00 |
75.37 |
C |
|
2 |
I&D Zone-I |
I&D |
123.64 |
13/07/1995 |
31/05/1997 |
100 |
194.88 |
00.00 |
194.88 |
C |
|
3 |
I&D Zone-II |
I&D |
141.40 |
23/11/1994 |
31/05/1997 |
100 |
220.62 |
00.00 |
220.62 |
C |
|
4 |
I&D Zone-III A |
I&D |
258.37 |
11/01/1995 |
31/05/1997 |
100 |
376.32 |
00.00 |
376.32 |
C |
|
5 |
I&D Zone-III B |
I&D |
212.50 |
23/02/1995 |
31/05/1997 |
100 |
257.82 |
00.00 |
257.82 |
C |
|
6 |
Land Acquisition for STP-I |
LA |
16.78 |
13/12/1996 |
30/06/1997 |
100 |
160.73 |
00.00 |
160.73 |
C |
|
7 |
Land Acquisition for STP-II |
LA |
71.50 |
13/12/1996 |
30/06/1997 |
100 |
71.50 |
00.00 |
71.50 |
C |
|
8 |
Land Acquisition for STP-III |
LA |
137.50 |
13/12/1996 |
30/06/1997 |
100 |
195.32 |
00.00 |
195.32 |
C |
|
9 |
Public Participation |
PP |
10.80 |
08/12/1999 |
29/02/2000 |
100 |
00.00 |
00.00 |
00.00 |
C |
|
10 |
MPS Zone -I(20 mld) |
MPS |
253.64 |
23/12/1996 |
30/04/1997 |
100 |
238.11 |
00.00 |
238.11 |
C |
|
11 |
MPS Zone -II(45 mld) |
MPS |
319.55 |
23/12/1996 |
30/04/1997 |
100 |
300.41 |
00.00 |
300.41 |
C |
|
12 |
MPS -Zone -III(50 mld) |
MPS |
629.33 |
26/12/1996 |
30/04/1997 |
100 |
586.47 |
00.00 |
586.47 |
C |
|
13 |
Sewage Treatment Plant-I(20 mld) |
STP |
470.00 |
12/05/1996 |
30/04/1997 |
100 |
641.78 |
00.00 |
641.78 |
C |
|
14 |
Sewage Treatment Plant-II(45 mld) |
STP |
1107.00 |
12/05/1996 |
30/04/1997 |
100 |
1464.38 |
00.00 |
1464.38 |
C |
|
15 |
STP-III (50 mld) |
STP |
1170.00 |
12/05/1996 |
30/04/1997 |
100 |
1523.01 |
00.00 |
1523.01 |
C |
|
16 |
IPS Zone -III A |
IPS |
331.34 |
24/12/1996 |
31/05/1997 |
100 |
304.41 |
00.00 |
304.41 |
C |
|
17 |
Improved Wood Crematoria |
IWC |
02.97 |
21/07/1994 |
31/05/1997 |
100 |
04.39 |
00.00 |
04.39 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
5324.70 |
6615.52 |
00.00 |
6615.52 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |