SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
EXTENDED YAMUNA ACTION PLAN |
||||||||||
|
STATE : UTTAR PARDESH |
||||||||||
|
CITY : ETAWAH |
||||||||||
|
1 |
Public Participatipn |
PP |
10.00 |
31/03/2002 |
100 |
09.99 |
00.00 |
09.99 |
C |
|
|
2 |
Lining Works of STP |
P-S |
14.29 |
06/08/2001 |
28/02/2002 |
100 |
12.13 |
00.00 |
12.13 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
24.29 |
22.12 |
00.00 |
22.12 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |
|
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN |
||||||||||
|
STATE : UTTAR PARDESH |
||||||||||
|
CITY : ETAWAH |
||||||||||
|
1 |
Afforestation |
AFF |
03.90 |
02/12/1998 |
100 |
02.91 |
00.00 |
02.91 |
C |
|
|
2 |
Low Cost Sanitation |
LCS |
60.76 |
15/06/1994 |
100 |
70.32 |
00.00 |
70.32 |
C |
|
|
3 |
Interception & Diversion |
I&D |
25.81 |
20/02/1995 |
01/03/1996 |
100 |
65.18 |
00.00 |
65.18 |
C |
|
4 |
Land Acquisition |
LA |
100.00 |
13/05/1994 |
100 |
52.00 |
00.00 |
52.00 |
C |
|
|
5 |
Public Participation |
PP |
10.80 |
11/11/1999 |
29/02/2000 |
100 |
10.13 |
00.00 |
10.13 |
C |
|
6 |
River Front Development |
RFD |
28.67 |
21/12/1998 |
31/10/1999 |
100 |
11.16 |
00.00 |
11.16 |
C |
|
7 |
STP & Effluent Channel |
STP |
241.67 |
18/10/1995 |
31/10/1997 |
100 |
375.22 |
00.00 |
375.22 |
C |
|
8 |
Improved Wood Crematoria |
IWC |
07.58 |
20/06/1994 |
31/03/1995 |
100 |
10.44 |
00.00 |
10.44 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
479.19 |
597.36 |
00.00 |
597.36 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |