SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
NATIONAL RIVER CONSERVATION PLAN |
||||||||||
|
STATE : KARNATKA |
||||||||||
|
CITY : DAVANAGERE |
||||||||||
|
1 |
Low Cost Sanitation |
LCS |
63.04 |
15/03/1996 |
30/12/1997 |
80 |
50.63 |
00.00 |
50.63 |
O |
|
2 |
Interception & Diversion Phase-I |
I&D |
13.12 |
13/12/1996 |
30/06/1998 |
100 |
15.81 |
00.00 |
15.81 |
C |
|
3 |
Interception & Diversion Phase-II |
I&D |
151.62 |
05/06/1997 |
31/05/1998 |
100 |
148.56 |
00.00 |
148.56 |
C |
|
4 |
River Front Development |
RFD |
03.90 |
15/03/1996 |
30/09/1996 |
100 |
03.90 |
00.00 |
03.90 |
C |
|
5 |
Bathing Ghat |
RFD |
06.93 |
03/02/2004 |
31/08/2004 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
6 |
Sewage Treatment Plants (Based on WSP) |
STP |
180.80 |
22/06/2000 |
30/11/2001 |
100 |
186.44 |
00.00 |
186.44 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
419.41 |
405.34 |
00.00 |
405.34 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW-->
BOUNDRY WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D, CRE-->
ELECTRIC CREMATORIA |
|
|
RM--> RISING MAIN, I&D-->
INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC PARTICIPATION, OTH-->
OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT, STP-->
SEWAGE TREATMENT PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST
YARD |
|
|
PLC--> PART OF LCS |