SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]

 












S.NO.

SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE : KARNATKA

CITY : DAVANAGERE

1

Low Cost Sanitation

LCS

63.04

15/03/1996

30/12/1997

80

50.63

00.00

50.63

O

2

Interception & Diversion Phase-I

I&D

13.12

13/12/1996

30/06/1998

100

15.81

00.00

15.81

C

3

Interception & Diversion Phase-II

I&D

151.62

05/06/1997

31/05/1998

100

148.56

00.00

148.56

C

4

River Front Development

RFD

03.90

15/03/1996

30/09/1996

100

03.90

00.00

03.90

C

5

Bathing Ghat

RFD

06.93

03/02/2004

31/08/2004

0

00.00

00.00

00.00

O

6

Sewage Treatment Plants (Based on WSP)

STP

180.80

22/06/2000

30/11/2001

100

186.44

00.00

186.44

C












TOTAL

419.41

405.34

00.00

405.34












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION, BW--> BOUNDRY WALL, LCS--> LOW COST SANITATION

PID--> PART OF I&D, CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN, I&D--> INTERCEPTION & DIVERSION, LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION, OTH--> OTHER(MISCELLANEOUS WORK), MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT PLANT, P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION, IWC--> IMPROVED WOOD CREMATORIA, SWM--> COMPOST YARD

PLC--> PART OF LCS