SANCTION/PROGRESS OF
SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC. |
SANC |
COMP DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
NATIONAL RIVER CONSERVATION PLAN |
||||||||||
|
STATE : MADHYA PRADESH |
||||||||||
|
CITY : BURHANPUR |
||||||||||
|
1 |
Afforestation |
AFF |
00.70 |
27/05/1998 |
100 |
00.65 |
00.00 |
00.65 |
C |
|
|
2 |
Low Cost Sanitation |
LCS |
37.71 |
08/01/1997 |
31/07/1997 |
100 |
37.09 |
00.00 |
37.09 |
C |
|
3 |
Interception & Diversion |
I&D |
158.79 |
13/02/1996 |
31/01/1998 |
100 |
89.14 |
00.00 |
89.14 |
C |
|
4 |
Land Acquisition |
LA |
08.31 |
15/02/1996 |
30/06/1996 |
100 |
00.05 |
00.00 |
00.05 |
C |
|
5 |
River Front Development |
RFD |
55.19 |
05/06/1997 |
30/06/1998 |
100 |
41.53 |
00.00 |
41.53 |
C |
|
6 |
Sewage Treatment Plant (10 mld) |
STP |
289.25 |
14/07/2003 |
31/01/2005 |
100 |
213.50 |
00.00 |
213.50 |
C |
|
7 |
Improved Wood Crematoria |
IWC |
07.07 |
08/01/1997 |
31/07/1997 |
100 |
05.85 |
00.00 |
05.85 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
557.02 |
387.81 |
00.00 |
387.81 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C --> COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF--> AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE
PUMPING STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |