SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












NATIONAL RIVER CONSERVATION PLAN

STATE :  TAMILNADU

CITY :  BHAWANI

1

Low Cost Sanitation

LCS

23.71

14/02/1996

100

24.29

00.00

24.29

C

2

Interception & Diversion

I&D

264.59

31/03/2005

31/12/2005

80

142.01

00.00

142.01

O

3

River Front Development

RFD

29.20

13/02/1996

10/09/1996

100

18.88

00.00

18.88

C

4

Sewage Treatment Plant (3.94 mld, WSP)

STP

53.19

19/06/2002

31/12/2003

100

49.28

00.00

49.28

C

5

Improved Wood Crematoria

IWC

01.14

13/02/1996

30/06/1996

0

00.00

00.00

00.00

O

6

Compost Yard

SWM

23.24

15/02/1996

30/09/1996

5

06.27

00.00

06.27

O












TOTAL

395.07

240.73

00.00

240.73












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS