SANCTION/PROGRESS
OF SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME
NAME |
TYPE |
SANC. |
SANC |
COMP
DATE |
%PHY |
C.EXP |
EXP. |
C.EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
|
GANGA
ACTION PLAN - II(MAIN STEM) |
||||||||||
|
STATE
: WEST BENGAL |
||||||||||
|
CITY
: BADRESHWAR-CHAM |
||||||||||
|
1 |
Afforestation |
AFF |
02.24 |
05/08/2004 |
31/12/2005 |
100 |
02.25 |
00.00 |
02.25 |
C |
|
2 |
Interception
& Diversion |
I&D |
157.23 |
09/09/2002 |
30/04/2004 |
100 |
157.20 |
00.00 |
157.20 |
C |
|
3 |
Lifting
Station |
I&D |
92.41 |
09/09/2002 |
30/06/2004 |
100 |
92.35 |
00.00 |
92.35 |
C |
|
4 |
Lifting
Station (Part-B) |
I&D |
46.26 |
31/07/2003 |
31/07/2005 |
100 |
46.15 |
00.00 |
46.15 |
C |
|
5 |
Additional
Lifting Station |
I&D |
192.10 |
20/05/2005 |
28/02/2006 |
100 |
163.71 |
25.83 |
189.54 |
C |
|
6 |
Public
Participation & Awareness Programme |
PP |
11.34 |
25/08/2004 |
31/12/2005 |
100 |
02.39 |
00.00 |
02.39 |
C |
|
7 |
River
Front Development |
RFD |
13.61 |
14/08/2002 |
30/09/2003 |
100 |
13.61 |
00.00 |
13.61 |
C |
|
8 |
River
Front Development |
RFD |
130.64 |
02/08/2004 |
31/08/2006 |
100 |
130.65 |
00.00 |
130.65 |
C |
|
9 |
Sewage
Treatment Plant (Part-B) |
STP |
64.75 |
30/07/2003 |
31/07/2005 |
100 |
60.57 |
04.18 |
64.75 |
C |
|
10 |
Sewage
Treatment Plant |
STP |
157.20 |
31/07/2003 |
31/07/2005 |
100 |
157.18 |
00.00 |
157.18 |
C |
|
11 |
STP
at Badreshwar town |
STP |
30.10 |
20/07/2005 |
31/12/2005 |
100 |
30.00 |
00.00 |
30.00 |
C |
|
12 |
Sewage
Treatment Plant |
STP |
39.50 |
05/02/2008 |
31/07/2008 |
100 |
42.38 |
00.00 |
42.38 |
C |
|
13 |
Sewage
Treatment Plant |
STP |
06.50 |
05/02/2008 |
31/07/2008 |
100 |
06.50 |
00.00 |
06.50 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
943.88 |
904.94 |
30.01 |
934.95 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
#
--> REFERS
TO REVISED COST AND REVISED DATE | |
|
*
--> REFERS
TO SCHEMES NOT YET APPROVED | |
|
C
--> COMPLETED, O--> ONGOING, D--> DROPPED | |
|
AFF--> AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW
COST SANITATION | |
|
PID--> PART
OF I&D, CRE--> ELECTRIC
CREMATORIA | |
|
RM--> RISING
MAIN, I&D--> INTERCEPTION
& DIVERSION, LA--> LAND
ACQUISTION | |
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN
PUMPING STATION | |
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE
TREATMENT PLANT, P-S--> PART
OF STP | |
|
IPS--> INTERMEDIATE
PUMPING STATION, IWC--> IMPROVED
WOOD CREMATORIA, SWM--> COMPOST
YARD | |
|
PLC--> PART
OF LCS |