SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












GANGA ACTION PLAN - II(MAIN STEM)

STATE :  BIHAR

CITY :  BARAHYA

1

Low Cost Sanitation

LCS

13.37

01/10/1996

31/08/1997

100

10.26

00.00

10.26

C

2

River Front Development

RFD

32.85

03/10/1996

31/08/1997

100

27.63

00.00

27.63

C












TOTAL

46.22

37.89

00.00

37.89












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS