SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 












S.NO.

    SCHEME NAME

TYPE

SANC.
COST
TILL
MAR.11

SANC
DATE
TILL
MAR.11

COMP DATE

%PHY
PRG

C.EXP
TILL
MAR.10

EXP.
DURING
CURRENT
YEAR
2010-2011

C.EXP
TILL
MAR.11

STATUS












GAP II

STATE :  UTTAR PARDESH

CITY :  ANUPSHAHER

1

Low Cost Sanitation

LCS

45.83

16/06/1997

30/09/1998

100

43.42

00.00

43.42

C

2

Interception & Diversion (Part-I)

I&D

220.37

18/05/2001

31/05/2003

100

214.51

00.00

214.51

C

3

I&D Part-II (Zone-B)

I&D

132.79

23/07/2001

31/07/2003

100

136.08

00.00

136.08

C

4

Sewage Treatment Plant(Bullandshahr)

STP

53.80

26/06/2003

31/12/2004

100

51.08

00.00

51.08

C












TOTAL

452.79

445.09

00.00

445.09












 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS