GANGA ACTION PLAN PHASE-II (Main Stem) * |
||
|
|
|
|
|
|
|
(Rupees in
Crores) |
|
YEAR OF LAUNCH |
: |
July 1995/Oct. 1996 (For W.B.) |
|
SCHEDULE OF COMPLETION |
: |
March 1999/Dec. 2001
(For W.B.) |
|
COST SANCTIONED
(till 3/10) |
: |
Rs. 591.43 |
|
FUND RELEASED
(till 3/10) |
: |
Rs. 410.49 |
|
FUND UTILISED
(till 3/10) (Including State Share) |
: |
Rs. 430.57 |
|
FINANCIAL PROGRESS
(%) |
: |
72.80% |
|
NO. OF SCHEMES
SANCTIONED |
: |
315 |
|
NO. OF SCHEMES
COMPLETED |
: |
257 |
|
STATES COVERED |
: |
8 |
|
TOWNS COVERED |
: |
60 |
|
RIVERS COVERED |
: |
3 |
|
STP CAPACITY SANCTIONED |
: |
275.51
mld |
|
STP CAPACITY CREATED |
: |
185.95 mld |
|
*à Includes
Mahananda River |
|
|
_files/image002.gif)