|
8. N0N-TECHNICAL SUMMARY |
|||||||
|
|
|
|
|
|
|
|
|
|
No. |
Criterion |
|
Relevant? (Y/N) |
|
Judgement (C/A/I) |
|
Comment |
|
|
|
|
|
|
|
|
|
|
8.1 |
Does the information
contain at least a brief description of the project and the environment, an
account of the main mitigation measures to be undertaken by the developer,
and a description of any remaining or residual impacts? |
|
|
|
|
|
|
|
8.2 |
Have technical terms,
lists of data and detailed explanations of scientific reasoning been avoided
in the summary? |
|
|
|
|
|
|
|
8.3 |
Does the non-technical
summary present the main findings of the assessment and cover all the main
issues? |
|
|
|
|
|
|
|
8.4 |
Does the summary provide
an indication of the confidence that can be placed in the results? |
|
|
|
|
|
|
|
|
Other Relevant Criteria[1] |
|
|
|
|
|
|
|
8.5 |
|
|
|
|
|
|
|
|
8.6 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8 Non-Technical Summary: Appraisal of Review Area |
||
|
The reviewer can use this Area Checklist to derive a single appraisal
of the quality of environmental information submitted within each Appraisal
Area. An appraisal of the information
could be made according to the following system (which may then form input
into the overall project appraisal at the end of the checklist). |
||
|
Score |
Grade |
Criteria |
|
2 |
Excellent : |
The environmental information contains everything required for
decision-making on the project. There
are no gaps. |
|
1 |
Good : |
The environmental information contains most of the information
required as far as it is relevant in the particular circumstances of this
project; any gaps are relatively minor. |
|
0 |
Satisfactory : |
The information presented is not complete; there are significant
omissions but in the context of the proposed project, these are not so great
as to prevent a decision being made on whether the project should be allowed
to proceed. |
|
-1 |
Inadequate : |
Some of the information has been provided but, there are major
omissions; in the context of the proposed project these must be addressed
before a decision on whether the project should be allowed to proceed can be
taken. |
|
-2 |
Poor : |
The information required has not been provided or is far from
complete and, in the context of the proposed project, the omissions must be
addressed before a decision in whether the project should be allowed to
proceed can be taken. |
I recommend that this Review
Area be assigned the following:
|
Grade |
|
Score |
|
Comment (where a score is less than or equal to
zero, and, where appropriate and feasible, please expand on recommended
future actions) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
OVERALL APPRAISAL OF THE INFORMATION |
This section will allow for the overall appraisal of the project
proposal..
|
No. |
Review Area |
|
Score |
|
Judgement (C/A/I) |
|
Comment |
|
|
|
|
|
|
|
|
|
|
1 |
DESCRIPTION OF THE PROJECT |
|
|
|
|
|
|
|
2 |
PROJECT AND PROCESS ALTERNATIVES |
|
|
|
|
|
|
|
3 |
DESCRIPTION OF THE ENVIRONMENT |
|
|
|
|
|
|
|
4 |
DESCRITPTION OF IMPACTS |
|
|
|
|
|
|
|
5 |
MITIGATION MEASURES |
|
|
|
|
|
|
|
6 |
DIFFICULTIES COMPILING INFORMATION |
|
|
|
|
|
|
|
7 |
GENERAL PRESENTATION |
|
|
|
|
|
|
|
8 |
NON-TECHNICAL SUMMARY |
|
|
|
|
|
|
|
|
OVERALL ASSESSMENT (Total
Score) : |
|
|
|
|
|
|
|
I recommend that this
proposal (please indicate): |
|
Be returned |
|
Be Processed |
|
Go for Expert Review |
|
|
|
|
|
|
|
|
|
|
Comments |
|
|
|
|
|
Signed :
Date:
................................ Desk :
..
(1) [1] Insert here other criteria, if any have been identified, which are considered relevant in the specific circumstances of the development.