Procedure for Submitting
CDM Project Reports to the National CDM Authority
The National CDM Authority is a single window clearance
for CDM projects in the country. The project proponents
are required to submit one soft copy of Project Concept
Note (PCN) and Project Design Document (PDD) through
online form and 20 hardcopies each of PCN and PDD along
with two CDs containing all the information in each
of them.
The project report and CDs should be forwarded through
covering letter signed by the project sponsors. The
project report submitted should be properly bound. The
National CDM Authority examines the documents and if
there are any preliminary queries the same are asked
from the project proponents. The project proposals are
then put up for consideration by the National CDM Authority.
The project proponent and his consultants are normally
given about 10-15 days notice to come to the Authority
meeting and give a brief power point presentation regarding
their CDM project proposals. Members seek clarifications
during the presentation and in case the members feel
that some additional clarifications or information is
required from the project proponent the same is informed
to the presenter. Once the members of Authority are
satisfied, the Host Country Approval (HCA) is issued
by the Member-Secretary of the National CDM Authority.
|